Crook, Horner & Co. v. Baltimore & Ohio Railroad
Page, J., delivered the opinion of the Court. This appeal is from an order of the Court below, sustaining the exceptions of the appellees to the allowance by the Auditor of the claim of the appellants. On the fifteenth day of May, 1890, Charles Webb, the Receiver of the Bay Ridge Company, through his agent, Hugh L. Bond, Jr., contracted with a certain William H. Pitcher for the purchase of an ice machine, to be furnished within thirty days, with capacity for making one and one-half tons of ice per day, and for cooling to a temperature of thirty-two degrees Fahrenheit, in all weathers, certain specified spaces in the restaurant building at Bay Ridge. By the agreement Pitcher guaranteed the capacity and character of the machine, and agreed to .run the same for ten days after completion to demonstrate its efficiency; the Receiver to supply the water and steam required.
The price of the machine was to be $4,500, to be paid in instalments at different periods, with interest thereon from the date of acceptance, to be secured by notes endorsed by the B. & O. Railroad Co., or some individual endorser satisfactory to said Pitcher. It was also agreed that the • property in the machine should remain in Pitcher until the delivery of the notes, endorsed as stated; and these were not to be given until the machine was complete and working to the satisfaction of Mr. Bond. Pitcher put up the machine during the summer of 1890. On the thirtieth day of October, of the same year, the Receiver reported to the Court, that “ while the machine was partially operated the season of 1890, it 343 was not completed and working as required until after the close of the season, and your Receiver did not escape all expense on account of ice, as he had hoped.
Your Receiver has therefore agreed with said Pitcher, subject to the approval of this Honorable Court, to accept the said machine and apparatus; provided, the said Pitcher shall obtain the contract and agreement of Messrs. Crook, Horner & Co., a responsible firm of the city of Baltimore, to put the same in good working order at the beginning of the season of 1891, and to guarantee the same, shall in all respects comply with the requirements of the said contract between the said Receiver and said Pitcher, as well when operated during the summer months as at other times, and to pay for the same the sum of $2,000, on or before the 10th of July, 1891, and $2,000 on or before Sept. 1st, 1891, the balance in cash.” By an order passed on the 31st of October, the Court approved of the proposed contract and authorized him to issue his certificates of indebtedness bearing six per cent, interest per annum, to meet the deferred payments. On the 10th day of November ensuing, the Receiver entered into the following contract: “ Whereas, one William H. Pitcher did contract and agree with the said Receiver, by written agreement dated the 15 th of May, 1890, to construct and supply ice making and refrigerating plant at Bay Ridge, Anne Arundel County, Maryland, of the description mentioned in said contract, a copy of which is hereto annexed, referred to and made part of this agreement; and whereas, the said machinery and plant were not completed within the time mentioned in said contract, and could not be tested at the time therein provided; and whereas, the said Pitcher and the said Crook, Horner & Co., as his assignees, are desirous of obtaining a settlement from the said Receiver, and the Circuit Court for Anne Arundel County has authorized said Receiver to issue Receiver’s certificates to the amount of $4,000; to pay for said plant; provided, said firm of Crook, Horner & Co. will contract and agree to put the said machinery and plant 344 in good working order at the beginning of the season of 1891, and guarantee that the same shall, in all respects,, come up to the requirements of the said contract between said Receiver and Pitcher, as well when operated during the summer months as at other times. Now, * * * in consideration of the delivery by the said Receiver of four.
Receiver’s certificates, each for the sum of $1,000, bearing, &c., &c., and the payment of $293.15-100 in cash, in full settlement and payment for said ice machine and refrigerating plant, under said contract between the Receiver and the said' Pitcher, the said Crook, Horner & Co. do hereby promise, &c., that they will put said machine and apparatus in complete working order at the beginning of the season of 1891, by the fifteenth day of May, and will cause the same to comply with and come up to, in all respects, the requirements of said contract hereto attached, as well when operated during the summer months as at any time.” The amount provided to be paid under this agreement, that is, $4,293.15, was in full settlement for the machine and refrigerating plant, but it also comprehended payment for balance due for a pump located on the steamboat wharf. In pursuance of this contract, the cash provided for therein was paid, and certificates were issued payable to Pitcher, and upon being endorsed by him were delivered to the appellants. Two of these have been paid and the amounts due on the other two now constitute the appellee’s claim. It also appears, that prior to Nov., 1890, Pitcher had become largely indebted to Crook, Horner & Co., partly on account of money advanced to carry out his contract with the Receiver.
To secure this, Pitcher turned this
This is a preview of Crook, Horner & Co. v. Baltimore & Ohio Railroad. About 50% of the opinion remains. Read the complete opinion in RecordCite.