Maryland case law › Hampson v. Lewis ex rel. Marshall, Bingham & Bradford

Hampson v. Lewis ex rel. Marshall, Bingham & Bradford

49 Md. 178 (1878) · Maryland Court of Appeals
Maryland Court of AppealsDisposition: ReversedStewart, J.✓ Good law
SummaryThis was a bill in equity by a plastering contractor (Hampson) against a property owner (Lewis) to establish and recover a debt for work performed under an oral contract to plaster five houses for $1,500, with the owner to furnish materials. The complainant completed three houses and did partial work on the others, received $650, then abandoned the work, alleging the respondent failed to furnish necessary materials. The respondent denied the allegation, gave notice, and hired other mechanics to finish the plastering at a cost of $328, plus a $100 charge for his personal supervision. The testimony was conflicting, and the court held the burden of proof was on the complainant, who filed the bill to establish his debt. The Court of Appeals found the parol contract was too indefinite as to time of furnishing materials and progress of work to be strictly binding, but that the complainant was
Questions presented
  • Whether the complainant was justified in abandoning the work because of the respondent's alleged failure to furnish necessary materials.
  • Whether the respondent was entitled to engage other mechanics to finish the work and hold the complainant liable for the consequent loss due to non-performance.
  • What amount, if any, was due the complainant under the contract after deducting payments made and the cost of completion.
📖 Open the full case in RecordCite — full opinion, AI chat, highlights & citator →

Stewart, J., delivered the opinion of the Court. Under the contract in this case, which was merely by parol, the parties not having signed any written agreement, the complainant engaged to plaster the five houses of the respondent for some fifteen hundred dollars. All the necessary materials, such as laths, lime and hair, &c., to be provided, and had ready as needed, by the respondent—the complainant, according to the tenor 180 and effect of the contract, to go on with all reasonable dispatch to complete the worlf. The complainant having other work, and respondent other engagements, it seems to have been left very much to the mutual convenience of the parties to proceed with the work as they were respectively inclined.

At all events this rmrst be its substantial interpretation, as the verbal stipulations are not sufficiently definite to make the contract more binding, as to the time of furnishing the materials or progress of the work after they were on hand. Certainly the proof of the contract is not clear as to when the work was to be done—the effect of the complainant’s obligation, would require him to do it in a reasonable time. It appears it was to be paid for as it progressed, according to the convenience of the respondent, and entirely when completed. With this loose understanding, the complainant commenced the work, and after completing three of the houses, and some partial work on the others, and receiving some six hundred and fifty dollars, abandoned the work because of alleged failure on the part of the respondent to furnish the necessary materials. 'I1 his is affirmed on the part of the complainant and denied by the respondent, .and the testimony is conflicting.

The onus of the proof is on the complainant, who files the bill to establish his debt. Under these circumstances after giving notice to the complainant, the respondent employed other mechanics to to finish the plastering, which it seems cost some three hundred and twenty-eight dollars, besides the charge of one hundred dollars made by the respondent for his personal supervision. Leaving out of the calculation any claim of the respondent by way of recoupment, for damages sustained by him, by reason of the non-performance of his contract by the 181 complainant., he will have paid for the work nine hundred and seventy-eight dollars, and this deducted from the fifteen hundred dollars, the contract price, as made out, would leave $522 due the complainant. (Decided 26th June, 1878.) As to the respondent’s claim for damages by the delay, it was competent for him at any time, after giving notice to the complainant to proceed with the work, and having the materials ready, if there was failure on the part of the complainant, to engage other parties to finish his work, and hold the complainant if he was delinquent, for the consequent loss sustained through his non-performance.

According to the testimony, we think the said five hundred and twenty-two dollars is the full extent of the complainant’s claim, and the decree of the Circuit Court must be modified accordingly, and the case will be remanded for that purpose. Decree reversed, and cause remanded.