Maryland case law › Laurel Race Course, Inc. v. Regal Construction Co.

Laurel Race Course, Inc. v. Regal Construction Co.

274 Md. 142 (1975) · Court of Appeals of Maryland
Court of Appeals of MarylandDisposition: ModifiedLevine, J.✓ Good law
HoldingLaurel Race Course contracted with Regal Construction to rebuild its racetrack according to plans and specifications prepared by Watkins and Associates, designated the 'Engineer' under the General Conditions.

Levine, J., delivered the opinion of the Court. The dispute which has resulted in this appeal was spawned from the lofty but earnest ambition of appellant, Laurel Race Course, Inc. (Laurel), to build “the best [race] track in the United States.” To the extent that it might not have fully attained such preeminence, it undoubtedly faults appellee, Regal Construction Company, Inc. (Regal), with whom it had contracted to rebuild its track. Its dissatisfaction with the quality of Regal’s performance under that contract led to Laurel’s refusal to pay a portion of the sum claimed for those services. As a consequence, Regal brought suit and, following a nonjury trial in the Circuit Court for Prince George’s County (Bowen, J.), obtained a judgment against Laurel in the amount of $67,276.17.

This appeal followed. As the first step in its quest, Laurel, in March 1972, engaged an internationally renowned engineering firm, Watkins and Associates, Inc. (Watkins) of Lexington, Kentucky. Later that spring, Laurel and Watkins entered into a contract whereby the latter agreed to design a plan for the reconstruction of the Laurel track and the installation of a complete drainage system. Watkins had achieved success in designing such “all-weather” tracks for a number of 144 racing courses throughout the world.

In addition to preparing a design, a set of specifications and other similar documents, Watkins was to have personnel in attendance during the construction phase. In June 1972, Regal submitted a bid proposal for the construction work. In doing so, it agreed to perform “in strict accordance with the terms and conditions of the specifications and contract documents . . . and the plans . . . and do such other work incidental thereto as [might] be ordered by the Engineer, at the unit or lump sum prices quoted in the attached ‘Bid Schedule.’ ” It also declared that it had “examined the site of the work and informed [it]self fully in regard to all conditions pertaining to the place where the work [was] to be done; [and] that [it had] examined the plans, specifications, and contract documents .. . .” It also agreed to “substantially complete all work on or before September 1, 1972, and to finish the job by September 15, 1972.” This document and the contract itself expressly made time of the essence. After becoming the successful bidder, Regal executed the usual panoply of documents which regularly attend such transactions.

Among them was the “General Conditions” which defined Watkins’s status as the “Engineer.” It was to “have general inspection and direction of the work as the authorized representative of the owner [Laurel].” It had “authority to reject work and materials which [did] not conform to the plans, specifications and contract documents, .. . [and to] decide all engineering questions . . . .” It was also charged with the duty to “interpret the meaning and requirements” of those documents and to “decide all disputes” that might arise thereunder. In order to “protect itself from loss,” Laurel was permitted to withhold partial payments from Regal if the latter failed “to remedy defective work” and for “other causes which in the opinion of the Engineer would justify [Laurel] in withholding such . . . payments.” In addition, the General Conditions allowed Laurel to “retain not less than [ten percent] of the amount [of each partial payment] until final completion and acceptance of all work covered by this 145 contract.” The General Conditions concluded with a guarantee by Regal of “all construction against defective materials, equipment and workmanship for a period of twelve months . . . .” This included a commitment to “replace such defective parts without cost to the Owner.” Essentially, the work to be performed by Regal consisted of the rehabilitation of both the dirt and turf tracks, and the installation of a surface and underground drainage system, including proposed lakes, most of which was designed primarily to provide a “faster” track under “all-weather” conditions. The specifications detailed rather minutely the gradation requirements for the various materials to be used in the base, subbase and cushion of the main track. In this connection, the specifications provided: “If any over-size rock, or other deleterious materials that could be harmful to a running horse, are incorporated within the base material during the storage, mixing, or hauling of the base soil, such harmful material shall be removed by the Contractor at his own expense.” With respect to the storm drainage system, the specifications provide that “[a] 11 pipes shall be laid with ends abutting and true to line and grade,” and that the “space between pipes shall be filled with a concrete mortar of proper consistency” as therein specified.

Both the subbase and blended base materials were to “be paid for at the contract unit price in-place and compacted to the required density.” Payment under the entire contract was to be made on a “unit price” basis, whereby the total amount to be paid Regal was to be determined by applying the unit prices contained in the bid proposal to the actual quantities “certified by the Engineer for the items enumerated in the Bid Schedule . . . .” The contract was dated July 3, 1972, and Regal apparently commenced its work shortly thereafter. Performance was neither substantially completed by September 1 nor fully completed by September 15. Regal professes to have substantially completed the work in accordance with the contract terms by September 25, and claims that it ultimately rendered complete performance. On September 28, 1972, after “turning over” the track to Laurel on the 25th, 146 Regal received a “punch list” of 18 items requiring its attention.

After Regal claimed in late November that it had remedied those deficiencies and therefore demanded payment in full, Watkins forwarded its recommendation that payment be withheld because: “During the construction of the base the Contractor permitted a large amount of rock and oversize material to become mixed with the clay and sand which were hauled from the source of supply and, in spite of repeated requests, did not make a reasonable effort to remove this material from the base while it was being placed. . . . [I]t has been necessary for [Laurel’s] crew to perform a large amount of maintenance work that would not have been required had the base been properly blended and compacted. “The condition of the track for the first three weeks resulted in justifiable complaints from the horsemen and could be traced directly to the failure of the Contractor to obtain adequate compaction and proper shaping of the inside ditch and drainage.” Having received the recommendation from Watkins that payment of the balance due be retained, Laurel refused to pay the sum of $110,931.91, representing the amount then claimed by Regal as the unpaid balance on the total contract amount of $786,401.35. The latter brought suit for this amount plus interest in February 1973. By the time of the trial in April 1974, the amount claimed by Regal under the written contract had been reduced to $49,648 plus interest because Laurel had made additional payments during the intervening period. In its declaration, Regal sought payment under two express contracts.

For its first cause of action, it claimed the $49,648 under the original contract to which we have alluded. The other claim, amounting to $42,657.48, was based on a verbal contract allegedly entered into during late December 1972, when a conference was held between the 147 parties to resolve the impasse which had arisen. The essence of this claim is that Laurel agreed to pay Regal for such additional work as the latter would thereafter perform, provided it was not found to have been necessitated by defective or incomplete performance under the basic written contract. Regal claimed that it was entitled to recovery under this theory for additional work it subsequently had performed in the summer of 1973.

At the trial, Regal’s witnesses claimed that the blended soil base material which it had supplied not only had met the contract specifications, but also had been approved by Watkins, whose personnel had been present throughout the construction stage. With respect to the 24-inch pipe which had been installed as part of the drainage system, Regal conceded that it had become separated in some places and was “out of alignment both horizontally and vertically,” but insisted that originally it had been “laid true to grade.” It recognized the likelihood, however, that the bed supporting the pipe had not been properly reinforced, and that not all the joints had been mortared. In regard to the verbal contract, Laurel claimed at the trial that rather than an additional agreement, what had emerged from the December 1972 conference was a request by Regal for a further opportunity to comply with the specifications under the original contract. Laurel maintained that shortly after Regal “turned over” the track on September 25, 1972, stones were observed on the cushion of the track that had “worked up from the base.” This was initially observed during the training season which had preceded the racing season.

To assuage the horsemen, who were fearful of injuries to the horses and the jockies, Laurel found it necessary to perform a considerable amount of work with its own employees and equipment. Laurel sought to recoup the expenses incurred for this labor and equipment by backcharging Regal. This claim also included a charge for Laurel equipment that was used by Regal in an effort to bring the track into conformity with the specifications. When Regal returned to the site in the summer of 1973, it did some additional work on the base of the track in the 148 form of “remixing and reblending.” Expert soil engineers employed by Watkins testified that these efforts had improved the quality of the track, but had not brought it into compliance with the specifications because of stones and excessive clay content.

They pointed out that any stone greater than V8 of an inch was too large for a racetrack, and that such stones were “coming out of” the ten-inch soil base. The principal difficulty caused by the excessive clay content is that in rainy weather it expands and slows up the horses because it drains poorly. The witnesses acknowledged that they had observed the oversize stones in the material being installed by Regal in 1972, but were repeatedly assured by the latter’s construction superintendent, who said “ ‘I’ll get them out.’ ” There had been testimony that during the construction stage, Regal employees were “out with buckets, they were handpicking [the stones].” The expert testimony on behalf of Laurel was that only the part of the 24-inch pipe which did not run under the track could be unearthed, but an inspection of that part indicated it had not been laid true to grade; that the joints were not closed tightly and had not been mortared; and the “lifting holes had not been plugged.” Hence, the pipe had not been installed in accordance with the specifications and was not functioning correctly. At the conclusion of the trial, the court said with respect to the stones, “I hold everybody accountable for that: the contractor, the racetrack owner and the engineers.” Thus, it refused to recognize the presence of the stones as a deviation from contract performance.

In regard to the refusal of the engineer to furnish the certificate, the court found that “[Regal] had performed substantially all that [it] was asked or instructed to do”; and that the track was “substantially in conformance with what was expected.” Hence, it allowed the entire balance claimed under the written contract, $49,648. It also allowed $12,724.01 for the work which Regal had allegedly performed pursuant to the verbal contract. The court refused to allow Laurel any amount for the backcharges, although they were not controverted by any evidence. In addition to the total principal sum of $62,372.01, 149 the court allowed Regal interest in the amount of $4,904.16.

A portion of this interest was on part of the judgment itself, and the remainder was on the sums which Laurel had paid during the period intervening between the filing of suit and the trial. In urging reversal, Laurel advances these arguments: (1) That the trial court erred in overruling Laurel’s demurrer to count I of the declaration in which Regal had sought recovery upon the written contract. The demurrer was bottomed on the failure to allege production of the engineer’s final certificate — a condition precedent to Laurel’s liability. (2) That the trial court, having found that Regal had only substantially performed its written contract, erred in nevertheless awarding judgment for the full contract balance.

(3) That the trial court erred in granting recovery under the alleged oral contract without having first found the existence of such a contract; in any event, there was no evidence which would have supported such a finding. (4) That the court erred in allowing interest on the sums paid by Laurel prior to trial because, to that extent, the total recovery allowed exceeded the ad damnum clause of the declaration. In the view we take of this case, it becomes unnecessary for us to decide whether the demurrer should have been sustained, since the grounds on which it was filed are, in any event, embraced within our disposition on the written contract. (1) Following the trial court’s ruling on the demurrer, the case was tried on an amended declaration which included a claim under the written contract in count I and upon the oral contract in count II. 1 At the trial, Laurel persisted in its 150 contention, to no avail, that Regal failed to produce a certificate of the engineer as a condition precedent to liability under the written contract.

As we have indicated, the same argument is pressed on appeal. Almost a century ago, our predecessors held in Gill v. Vogler, 52 Md. 663, 666 (1879), where work was “to be done ... to the satisfaction of the City Commissioner [of Baltimore],” and payments during the progress of the work were to be made only in accordance with his “monthly estimates,” that those estimates were a condition precedent to recovery of such payments, absent bad faith or collusion. From that holding has emerged the general rule, followed uniformly by decisions of this Court, that where payments under a contract are due only when the certificate of an architect or engineer is issued, production of the certificate becomes a condition precedent to liability of the owner for materials and labor in the absence of fraud or bad faith, Chas. Burton Bldrs. v. L & S Constr., 260 Md. 66, 86 , 271 A. 2d 534 (1970); Pope v. King, 108 Md. 37, 45-47 , 69 A. 417 (1908); Filston Farm Co. v. Henderson, 106 Md. 335, 367 , 67 A. 228 (1907); 3A Corbin on Contracts, § 650 (1960); see Mann v. Philip Vizzini & Son, Inc., 263 Md. 471, 481 , 283 A. 2d 577 (1971).

Apart from fraud or bad faith, the only other exceptions to this rule are waiver or estoppel, Chas. Burton Bldrs. v. L & S Constr., supra, 260 Md. at 86-87 ; Filston Farm Co. v. Henderson, supra, 106 Md. at 369 . The durability of this rule may be more readily appreciated when one

This is a preview of Laurel Race Course, Inc. v. Regal Construction Co.. About 50% of the opinion remains. Read the complete opinion in RecordCite.