Manekin Construction, Inc. v. Maryland Department of General Services
Berger, J. This appeal arises from the circuit court’s order affirming the decision of the Maryland Board of Contract Appeals (the “Board”) to grant summary decision in favor of the Department of General Services of Maryland (“DGS”), appellee. On June 9, 2010, appellant Manekin Construction, LLC (“Mane-kin”) was awarded a contract with DGS to construct a two-story barrack and a one-story garage for the Maryland State Police in Hagerstown, Maryland. The contract price totaled more than eight million dollars and was subject to mutually agreed upon Proposed Change Orders (“PCOs”). As we discuss in detail below, Manekin submitted PCO No. 68 to DGS requesting additional compensation during the construction of the project.
After the project was complete, Manekin submitted a “Request for Equitable Settlement” on March 18, 2013. After DGS’s procurement officer denied Manekin’s claim for compensation, Manekin appealed to the Board. On September 17, 2016, during a hearing on the merits of the claim, the Board stopped the proceedings and granted DGS’s Third Motion for Summary Decision. The Circuit Court for Howard County affirmed the Board’s decision.
This appeal followed. The primary issue we must decide on appeal is whether the Board erred when it stopped the evidentiary hearing and granted summary decision in favor of DGS. More specifically, we must decide whether the Board improperly made findings of fact on disputed issues, including whether Manekin knew or should have known that DGS disputed or rejected Manekin’s request for compensation detailed in PCO No. 68. For the 159 reasons explained below, we hold that the Board erred in its decision to grant summary decision in favor of DGS.
BACKGROUND AND PROCEDURAL HISTORY Construction of the barrack and garage took place from June 21, 2010 until the project was substantially complete on or around July 26, 2012. Approximately every two weeks throughout the construction process, Manekin and DGS officials held meetings (“Progress Meetings”) to discuss Mane-kin’s progress and other issues. During performance of the construction, Manekin encountered certain difficulties that it attributed to delays caused by DGS (among other reasons) and submitted numerous PCOs, thereby requesting additional compensation. On November 2, 2011, Manekin notified DGS of the “cumulative impact and ripple effect of’ certain factors.
On December 7, 2011, Manekin submitted PCO No. 68, requesting compensation for the “additional time, and associated general conditions costs resulting from changes” discussed in the November 2, 2011 letter. A letter attached to PCO No. 68 detailed the changes requested, including the five “impact factors” that affected the cost of the project. Manekin and DGS discussed PCO No. 68 at three Progress Meetings, during which the issue was designated as “void” in the minutes for Progress Meetings and in the “PCO Log.” After the completion of the project, on or around March 18, 2013, Manekin sent a “Request for Equitable Settlement” to DGS requesting compensation for additional time caused by the same five impact factors as outlined in PCO No. 68. DGS denied the request in a letter dated April 3, 2013.
DGS indicated in its letter, “if you wish to further pursue this matter, you may do so in accordance with COMAR [Code of Maryland Regulations] 21.10.04 and the Contract Documents, General Conditions, Section 6.13, ‘Disputes and Contract Claims.’ ” On April 10, 2013, Manekin submitted its notice of claim, and on April 29, 2013, submitted its formal claim to the procurement officer. The procurement officer denied Mane-kin’s claim on November 12, 2013, finding that the notice of claim was not submitted within thirty days of when Manekin 160 knew or should have known of the basis of a claim. Manekin timely appealed to the Board. On September 17, 2016, the Board stopped the proceedings and granted DGS’s pending Third Motion for Summary Decision, finding that Manekin knew of the basis of its claim by no later than March 1, 2012, which was more than thirty days before Manekin submitted its notice of claim.
On September 21, 2015, the Board issued a written order. Manekin filed a petition for judicial review in the Circuit Court for Howard County. After a hearing on April 21, 2016, the circuit court affirmed the Board’s grant of summary decision in a written opinion issued on April 27, 2016. DGS Contract & Relevant COMAR Provisions The “Department of General Services General Conditions for Construction Contracts (Revised March 2007)” contains the conditions of the contract between DGS and Manekin.
As required, the contract incorporates the language of COMAR 21.07.02.05-1. 1 Under a section of the contract entitled “6.13 Disputes and Contract Claims (COMAR 21.07.02.05-1),” the contract provides that it is “subject to the provisions of State Finance and Procurement Article, Title 15, Subtitle 2, Annotated Code of Maryland, and COMAR 21.10.” The following are other pertinent provisions incorporated in the contract from COMAR 21.07.02.05-1: B. Except as otherwise provided in this contract or by law, all disputes arising under or as a result of a breach of this contract that are not disposed of by mutual agreement shall be resolved in accordance with this clause. C. As used herein, claim means a written demand or assertion by one of the parties seeking, as a legal right, the payment of money, adjustment or interpretation of contract terms, or other relief, arising under or relating to this 161 contract. A voucher, invoice, or request for payment that is not in dispute when submitted is not a claim under this clause. However, if the submission subsequently is not acted upon in a reasonable time, or is disputed as to liability or amount, it may be converted to a claim for the purpose of this clause.
D. Within 30 days after Contractor knows or should have known of the basis for a claim relating to this contract, Contractor shall file a written notice of claim with the procurement officer. ⅜ * * F. The claim shall set forth all the facts surrounding the controversy. Contractor, at the discretion of the procurement officer, may be afforded an opportunity to be heard and to offer evidence in support of the claim. PCO No. 68 On December 7, 2011, Manekin submitted PCO No. 68 providing two methods for calculating the amount of compensation it asserted to be due for the five impact factors discussed in PCO No. 68—a “Change Order Analysis” and a “Measured Mile Approach.” Manekin notes in the PCO that, although these two methods produced two different time calculations, they were intended to provide a basis for further negotiations. Manekin relied on its “General Requirements Costs” of $1,315.00 per day, as provided in the original contract with DGS, and requested 96 days of “Contract Time Extension” plus other expenses, for a total of $128,134.00.
Within the PCO, however, Manekin “reserve[d] the right to request compensation for all direct and indirect costs attributable to this delay impact.” At the end of PCO No. 68, Manekin added, “We believe our calculations to be reasonable and an appropriate representation of the impacts to Manekin on this project. However, we are willing to meet and negotiate an acceptable compromise without this matter escalating to another level.” Thereafter, the parties’ representatives discussed PCO No. 68 at multiple Progress Meetings. 162 PCO Log The PCO Log is a record of all PCOs as well as each PCO’s status. The status of each PCO is indicated in the “Remarks/Days” column. Some of these status designations include “VOID,” “REJECTED,” “CREDIT,” and various phrases such as “No charge VOID,” “Located in PCO # 13 VOID,” or “G.C. agrees to amt.” Additionally, in the date column, either the date of the action is indicated or, if the PCO’s status is ‘VOID,” only the word ‘VOID” is listed in place of the date.
A column labeled “PCO AMT.” lists the amount requested for each PCO, and a column labeled “DGS EST.” lists the amount to be added to the total amount due to Manekin. For any item designated as “VOID,” the “DGS EST.” is either blank or has a value of “$0.00.” At the end of the PCO Log, the total “DGS EST.” indicated is $1,232,918.00. For PCO No. 68, which is described as “Time Extension Request to justify new schedule,” the table indicates a “PCO AMT.” of $128,134.00, and the term ‘VOID” is included under the “REMARKS/DAYS” column and in the date column. For comparison purposes, PCO No. 22 (“Soil Fill Material Phase # 1), which had a “PCO AMT.” of $117,642.00, is recorded as “REJECTED” in the “REMARKS/DAYS” column.
PCO No. 70 (“Revise Membrane @ Phse Chimney Caps”), on the other hand, is listed as “No charge VOID” and no amount was added to the total. Progress Meetings The record before the Board contained the minutes for each relevant Progress Meeting, including Progress Meetings 37, 38, and 39. The minutes for each Progress Meeting include the names of persons attending, who would receive a copy of the minutes, a synopsis of the progress of the project as of that date, and notes of the topics discussed at the meeting. The minutes from Progress Meeting 37, held on January 5, 2012, include a section entitled “Time Extension PCO Discussion” containing eighteen points of discussion.
The relevant portion of the minutes from Progress Meeting 37 includes the following: 163 14. J. Rohrbach tentatively said that with correct back-up: a. PCO 63—6 days b. PCO 68—VOID c.
PCO 73—10 days 16. Dan Sharpe offered March 1, 2012 and leave open on compensational [sic]. 2 ⅜ ⅜ 18. Tentative Schedule: —February 15, 2012—Develop ‘work list’ —March 1, 2012—Substantial Completion Punch List and begin Barrack move —Within 60 days (May 1, 2012) the following items will be placed on punch list and complete: —Abatement —Demo —Landscape —Paving —Fuel System The revised minutes for Progress Meeting 38, which was held on January 19, 2012, reference the need for “fragnets” for PCO No. 68. A fragnet is a detailed analysis of how particular factors impacted the construction project, such as when and how the contractor lost scheduled time.
The minutes indicate that the parties continued to discuss PCO No. 68, referenced by the following notation: VOIDED AA. PCO 068—Rock extension is not approved to April 14, 2012. Day after Jan. 27, 2012 Liquidated Damages will be accessed [sic]. Fragnets must be submitted and part of the time extension. 164 01-05-12 VOIDED.
Finally, the minutes from Progress Meeting 39, held on February 2, 2012, included the same notations under points 14, 15, and 18 as the minutes from Progress Meeting 37, with the addition of the following notes added to point 18: 01-19-12 52 days currently being allowed for extension. 02-02-12 Substantial Complete is now May 1st (Added 131 days) Hearing Before the Board and the Board’s Decision In a letter dated August 7, 2015 from Board Member Dana Dembrow, the Board notified the parties of the trial date for Manekin’s appeal of the procurement officer’s denial of its claim. The brief letter included the following: As you know, there are three (3) Motions pending for Partial Summary Decision in this matter, which is currently scheduled for trial on September 14, 2015. Counsel understand that the pending Motions must be based on factual matters as to which there is no genuine dispute, and that all factual inferences must be resolved in favor of the adverse party at this point in the proceeding. At the present time, the Board does not anticipate making any decision on the pending Motions until after evidence is presented at trial.
Of course, counsel are also free to renew Motions during the course of trial as evidence is adduced. We hope this correspondence is useful to your trial preparation. Hearings before the Board were held on September 14, 16, and 17, 2016. The only witness to testify before the Board ended the proceedings by granting DGS’s motion for summary decision was Daniel Sharpe, Vice President and Project Manager for Manekin.
Sharpe testified regarding when he became aware that DGS had denied the request contained in PCO No. 68. The following colloquy between the Presiding Member of the Board and counsel for DGS ensued: 165 PRESIDING MEMBER DEMBROW: ... Now, frankly, ... there’s nothing in this affidavit that says what Mr. Rohrbach intended by the word void or voided. And that’s the crux of the issue. [... ] We’re still trying to figure out what was meant by void.
So hopefully we’ll get to that point. [...] [YJou’ve made a very effective point that the State told the Appellant this PCO 68 was void. Okay. [COUNSEL FOR DGS]: Mr. Dembrow, ... I gave you a Daniel Webster’s Dictionary definition of the word void. [...] You’re not going to get anything more from the State. We just—we use English words ....
And [counsel for Manekin] will agree with me, the word void isn’t defined anywhere in the contract. PRESIDING MEMBER DEMBROW: ... I’ve been waiting to hear from Mr. Rohrbach. In this affidavit he ... reiterates that he uses the word void.
It seems odd that he doesn’t say PCO 68 was rejected. What it says is it was void. And it further says that it was void with the opportunity to submit or the request and requirements to submit fragnets. And Mr. Sharpe, if we can [direct] your attention to the progress meeting on January 5, 2012 ... that’s where the progress meeting reports say, quote, Dan Sharpe offered March 1, 2012 and leave discussion open on compensational.
Whatever that means .... Counsel for DGS returned to questioning Sharpe and asked whether his belief “in his mind” that the issue in PCO No. 68 was left open had been documented. After Sharpe pointed to the Progress Meeting minutes notation “leave open on com-pensational [sic],” Presiding Member Dembrow added the following: PRESIDING MEMBER DEMBROW: I think he has ... I think that the progress meeting notes are consistent with what he said.
He’s saying that he asked for the compensation to be left open, and the minutes of the progress meeting say leave discussion open. Thereafter, Presiding Member Dembrow interrupted cross-examination to ask a question directed at counsel for DGS: 166 PRESIDING MEMBER DEMBROW: ... Mr. Rohrbach is not going to testify, is that correct? [COUNSEL FOR DGS]: I haven’t made that decision yet, sir. PRESIDING MEMBER DEMBROW: I’m curious to know why it says in the affidavit that he never told anyone that they could wait until a later date, but all the notes reflect that they’re asking for fragnets.
They’re requiring fragnets. They want proof that it’s on the critical path. Obviously there was an anticipation that [Manekin was] going to submit something or [DGS] wouldn’t have required and requested it. And ... that’s sort of a mystery at this point. [.,. ] [H]e voided and asked for fragnets.
That’s the dilemma. That’s the dichotomy. [COUNSEL FOR DGS]: No, no, no, that’s not what his ... if you .., Mr. Dembrow, it says that he repeatedly had questions—conversations with Chris Mentó where Dan Sharpe was not present and he repeatedly said this is what I need, and they never came forward. [...] PRESIDING MEMBER DEMBROW: That makes your claim clearer. I’m sure [counsel for Manekin] has a different point of view. We’re going to hear evidence about that. [,..] I interjected.
I’m putting the State on fair notice where we need, where at least I need clarification. And that goes to the question of what they meant when they said voided give us fragnets. We’re trying to get to that, and the parties have opposite points of view. So let’s just try to go through the ... evidence as we should with the next, with another question of Mr. Sharpe. [[Image here]] [Redirect by counsel for Manekin] Q. ...
Your request for payment ... for ripple effects, was that in dispute at the time you submitted it? A. No. Q. Was PCO 68 in dispute at the time you submitted it? A. No. 167 Chairman Collins interjected during redirect with additional questions directed at Sharpe, which were focused primarily on why Sharpe had not filed a claim after PCO No. 68 was marked “VOID.” A. ... I didn’t feel that I had any claim or anything at the time when I was going through these things initially ‘cause we were trying to work through them. * * * CHAIRMAN COLLINS: ...
Because you thought in your mind we can do it all at the end. When in reality the general conditions said you had to do it within 30 days of when you should have known. [...] That’s the trouble I’m having as a Board Member here— A. But Mr. Collins, what I would like to answer back— CHAIRMAN COLLINS: Yeah, [pjlease do. A. —is I really ... didn’t know ... I had a dispute going on.
I was asked to try to produce a fragnet which I worked vigorously to try to do, and I was—because I never could really produce that fragnet that stated all these different things, that’s the reason why I felt that ... I wasn’t like in a ... claim mode or this major dispute mode ‘cause I was still trying to figure a way to produce the evidence or the backup that the State was asking for. [... ] CHAIRMAN COLLINS: Yeah, but even though you knew, you knew that it was gone. A. Well, it wasn’t ... really gone. CHAIRMAN COLLINS: Well, yeah, it was really gone.
Mr. Mentó acknowledged it was really gone, and so did Mr. Rohrbaeh in this deposition say it was really gone. What he did say, so we are going to void this, and you can come back later. This is null and void. This is gone.
But you know if you can produce that fragnet down the road show me another PCO. Well when someone says that to me ... you got to say to yourself at that point, there’s a potential claim. [By counsel for Manekin] 168 Q. ... [The] question to you is was there a dispute that had arisen during this process that you could file a notice of claim? A. Not at the time ... Q. Why not?
A. Because we didn’t receive any official thing. Except I understand the conversations that were had, but we were still having basically ongoing meetings, ongoing discussions about a lot of different things on the project, and I didn’t get, until I got that letter slammed back at me[,] that was when I realized I didn’t really have a— Q. Which letter? A. ... It was a letter that came back from the State which was from DGS that basically denied ... everything,...
Q. ... Mr. Collins’ point was that you knew that there was at least that PCO 68 was void. [... ] A. Well it didn’t mean to me it was off the table. It meant to me that I still had to come back, ... and once I produced the additional backup that I could bring that thing back up. Near the conclusion of Sharpe’s testimony, the Board stopped the proceedings and granted DGS’s Third Motion for Summary Decision.
Presiding Member Dembrow provided the following rationale for the Board’s Decision: Okay. At this time there will not be a need for recross-examination because the Board has unanimously determined to grant the State’s Motion for Partial Summary Judgment Number 3. After listening carefully to the testimony of Mr. Sharpe, who is the Vice President of the Appellant Construction Company, Manekin, and the Project Manager on this job, it is clear that even giving the Appellant the benefit of all doubt the ripple effect claim was first raised to the State by correspondence November 2, 2011. It was formally submitted as a proposed change order on December 7, 2011.
And the very next day the State indicated to Appellant that that PCO was, quote, void, end quote. Now that was clear in the mind of some of the Members of the Board that that meant reject. But giving Appellant the benefit of all doubt, 169 because there is a bit of a nuance in that DGS also noted on that voiding of that PCO that they wanted fragnets. The Board notes that the last request, and there are a couple of them at least, that the State made of the Appellant to submit the fragnets needed to support PCO 68, the last reference to fragnet was made on January 19, 2012.
There was a progress meeting on February 2, 2012, and in the minutes of that progress meeting, the minutes being dated February 7, 2012, there is reference that Mr. Sharp[e] stated or at least the minutes state, quote, Dan Sharpe offered March 1, 2012 and leave discussion open on compen-sational, period. That’s certainly not an example of the greatest grammar because it’s somewhat difficult to know what that even means. But it does appear beyond a shadow of a doubt that on February 2, 2012, when PCO 68 was marked void there was no reference to fragnets at that point. There had not been a reference for the need for further documentation by way of fragnets since January 19, 2012.
At least as of February [2nd] Mr. Sharpe was saying we’ll do this by March 1, 2012. [COMAR 21.10.04.02] says ... a contractor shall file a written notice of a claim relating to a contract with the appropriate procurement officer within 30 days after the basis for the claim is known or should have been known. It appears that the basis of the claim was initially known back in November of 2011. It certainly was known as of February 2012. But this claim was not filed until a year later.
So even if we give the ... Appellant the benefit of all doubt and give them [until] March 1, 2012, as the trigger date for the beginning of that 30-day statute of limitations, we’re still a year late. And the Board is directed by [COMAR 21.10.04.02C], quote, a notice of a claim or a claim that is not filed within the time prescribed shall be dismissed. Emphasis on the word shall.
Fair or unfair, that [is] what the regulation requires. [...] The Board has no choice but to not address the substantive merits of a claim that is filed a year late. And the Board concludes that that is the correct categorization of this 170 appeal. Therefore, it will be dismissed at this time without the necessity of further testimony. Presiding Member Dembrow confirmed that the other Board Members concurred in the decision before adding the following: We wanted to hear testimony from Mr. Sharpe and give the Appellant the benefit of all doubt.
We are comfortable that we’ve done that now. So this was not a decision made in haste, but one that we’ve been thinking about for a long time. And the testimony ... confirmed the view of some of the Board Members a long time ago. The Circuit Court’s Affirmance of the Board’s Decision On April 27, 2016, the Circuit Court for Howard County affirmed the Board’s decision to grant summary decision.
The written opinion of the circuit court provides, in pertinent part: The parties’ first dispute is over the standard of review to be applied by the Circuit Court in reviewing the decision of an administrative agency.... Specifically, Manekin argues that the VOID notation indicated it was to provide more documentation or information, and that it’s right to appeal did not attach until its more formal claim letter was denied 14 months later. [... ] DGS reminds the Court that because of the MSBCA members’ familiarity with the subject matter, state procurement law, and expertise in that area, the appellate decisions and statutes allow the Court a very limited scope of review. [...] When the Court is reviewing a final decision of an administrative agency, the Court determines the legality of the decision and whether there was “substantial evidence” from the record as a whole to support the decision. [...] Case law is clear that the Circuit Court[ ] is not to make findings of fact. That function is entirely within the realm of the agency, as is determining the inferences to be drawn from those facts. [...] Even though the final decision was reached by way of a ruling on a motion for summary decision, and not as the result of a contested hearing, the 171 analysis is the same.... The Court must determine if the findings of fact are supported in the record by substantial evidence, and if so, whether the decision of the agency was legally correct.
(Citations omitted). After articulating this standard of review, 3 the circuit court analyzed the Board’s decision and characterized the Board’s findings regarding notice as a “finding of fact.” The [Board] made a finding of fact that Manekin was on notice of DGS’s denial of its requests under PCO 68 by the end of February 2012 when Presiding Member Dana Dem-brow stated, “It appears that the basis of the claim was initially known back in November of 2011. It certainly was known as of February 2012. But this claim was not filed until a year later.
So even if we give the [ ] Appellant the benefit of all doubt and give them [until] March 1, 2012, as the trigger date for the beginning of that 80-day statute of limitations, we’re still a year late.” [...] This finding of fact was supported in the record by the Progress Meeting Notes for January 5, 2012, January 19, 2012, and February 2, 2012 which were received as evidence at the [Board] hearing. Reasoning minds examining this evidence could reasonably reach the conclusion that Manekin was on notice (knew or should have known) that DGS denied its claim for costs under PCO 68 by the end of February 2012. Inferences were resolved in Manekin’s favor when the Presiding Member gave Manekin until March 1, 2012. Thereafter, the circuit court affirmed the Board’s determination finding that DGS was entitled to summary decision as a matter of law.
DISCUSSION I. Judicial Review of an Agency’s Conclusions of Law The Court of Appeals has explained that we “look[ ] through the circuit court’s ... decision[ ], although applying 172 the same standards of review, and evaluate[ ] the decision of the agency.” People’s Counsel for Baltimore Cnty. v. Surina, 400 Md. 662, 681 , 929 A.2d 899 (2007). In other words, we “review! ] the agency’s decision, not the circuit court’s decision.” Long Green Valley Ass’n v. Prigel Family Creamery, 206 Md.App. 264, 273 , 47 A.3d
This is a preview of Manekin Construction, Inc. v. Maryland Department of General Services. About 50% of the opinion remains. Read the complete opinion in RecordCite.