Ross Contracting, Inc. v. Frederick County
NAZARIAN, J. This appeal arises from a construction contract between the Board of County Commissioners of Frederick County (the “County”) and Ross Contracting, Inc. (“Ross”), for the replacement of the Bidle Road Bridge. Among other things, the Contract required Ross to remove the bridge’s existing supporting abutments and excavate for new supports. In the course of excavating one of the abutments, Ross encountered subsurface conditions that differed from those it expected, so it filed a request for an equitable adjustment in the contract price to reflect the differences. The County denied Ross’s request.
An arbitrator appointed pursuant to the Contract 1 affirmed that denial in part, reversed it in part, and awarded Ross a smaller equitable adjustment than it had requested. The Circuit Court for Frederick County upheld the arbitration decision, finding substantial evidence in the record to support the arbitrator’s decision that Ross did not encounter a materially different site condition. Ross seeks our review, but we dismiss because Ross had no right of appeal to this court. I. BACKGROUND A. The Contract And Its Performance In October 2008, the County issued an Invitation to Bid (the “Invitation”) for a contract to construct the “Replacement of Bidle Road Bridge No. F03-10 over Catoctin Creek.” The Invitation called for the removal of the existing one-lane bridge structure and supporting abutments, excavation for new supports, and construction of a new two-lane bridge 568 structure and roadway (the “Project”).
Prospective bidders were also provided, among other things, with the Maryland State Highway Administration’s Standard Specifications for Construction and Materials (the “Specifications”) and four soil boring logs 2 of the excavation area, designated B-l through B-4, that indicated to bidders the types of subsurface materials at the excavation site. 3 Soil boring logs B-l and B-2 were from the area where Abutment A was to be constructed, and B-3 and B-4 were from the area where Abutment B was to be constructed. The soil boring logs for Abutment B indicated that the winning contractor should anticipate disintegrated rock down to a depth of 360 feet above sea level (“ASL”) at B-3 and 366.40 feet ASL at B-4. As such, the contract provided that the contractor would excavate to a depth of 382 feet ASL, where it would place the bottom of the footer for Abutment B. Ross, a construction company based in Mount Airy, reviewed the Invitation and, as part of the bid process, examined the Project site on four separate occasions. Ross was the successful low bidder and entered into a contract with the County on February 3, 2009 (the “Contract”).
The Contract incorporated, among other things, the Invitation, the Specifications, and the soil boring logs. The Specifications included specific provisions covering situations where site conditions during performance varied from the conditions set forth in the Contract: GP-4.05 Differing Site Conditions (a) The Contractor shall promptly, and before such conditions are disturbed, notify the procurement officer in writing of: 569 (1) Subsurface or latent physical conditions at the site differing materially from those indicated in this Contract; or (2) Unknown physical conditions at the site of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this contract. The procurement officer shall promptly investigate the conditions, and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performance of any part of the work under this Contract, whether or not changed as a result of such conditions, an equitable adjustment shall be made and the Contract modified in writing accordingly. (b) No claim of the Contractor under this clause shall be allowed unless the Contractor has given the notice required in (a) above; provided however, the time prescribed therefore may be extended by the State.
GP-4.06 Changes (d) ... [I]f any change under this clause causes an increase or decrease in the Contractor’s cost of, or the time required for, the performance of any part of the work under this Contract, whether or not changed by any order, an equitable adjustment shall be made and the Contract modified in writing accordingly. Provided, however, that except for claims based on defective specifications, no claim for any change under [4.06](b) above shall be allowed for any costs incurred more than 20 days before the Contractor gives written notice as therein required; and provided further, that in the case of defective Specifications for which the [County] is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with such defective Specifications. 570 (e) If the Contractor intends to assert a claim for an equitable adjustment under this clause, he shall, within 30 days after receipt of a written change order under [4.061(a) above or the furnishing of written notice under [4.061(b) above, submit to the procurement officer a written statement setting forth the general nature and monetary extent of such claim, unless this period is extended by the State[.] Overall, and before any adjustments, the County agreed to pay Ross in “an amount not to exceed the contract bid price of [$1,293,797.50].” Ross first completed demolition and excavation work on Abutment A, then began excavation activities for Abutment B on April 22, 2009. Excavation continued until April 29, when Ross encountered hard rock material above the elevations indicated on the boring logs provided by the County. The following day, Ross notified the County of what it believed to be a differing site condition, as described in GP-4.05.
The County suspended excavation activities on May 1. The County directed Ross to engage a third-party quality control/inspector subcontractor, ECS, Ltd. (“ECS”), to perform three additional borings in the area of Abutment B. ECS conducted the boring operations on May 11 and 12, 2009, and on May 18, it gave Ross a report of its findings (the “ECS Report”). The ECS Report indicated that hard rock materials existed at a depth of 389 feet ASL and that these materials differed from the conditions represented on the boring logs provided by the County. The County reviewed the ECS Report and, on May 26, 2009, informed Ross that it would issue a revised design of Abutment B. Two days later, Ross notified the County that it anticipated filing a claim for an equitable adjustment due to the differing site conditions and changed design.
On June 2, the County issued a “red-lined version of the Project designed for Abutment B,” which “raised” the bottom of the Abutment B footer by three feet — from 382 feet ASL to 385 feet ASL. The County noted that the newfound hard rock material made it unnecessary to excavate the additional three feet as original 571 ly planned because those depths would ultimately have been filled with concrete. Ross completed construction of the revised design on June 24, 2009 and, pursuant to GP-4.06(e), submitted a Proposed Change Order (the “PCO”) requesting an equitable adjustment of the Contract price in the amount of $89,971.55. Ross sought additional compensation for the added costs and time necessitated by the revised design, as well as the cost of ECS’s geotechnical exploration per the County’s direction.
In a letter dated July 27, 2009, the County rejected Ross’s PCO, stating that Ross was “only due a reasonable amount for the Geotechnical Services provided by ECS ... and that the credit due as a result of the raising of the bottom footing elevation ... may offset the additional inconvenience caused by the time it took to excavate the harder rock.” On November 17, 2009, Ross submitted a revised claim for $124,902.64, which the County also denied. In response, Ross invoked the Contract’s Arbitration provision: Pursuant to [Art. 25 § lA(g)], in the event of a dispute between the parties to this contract involving $10,000.00 or more regarding the terms of the contract or performance under the contract, the question involved in the dispute shall be subject to a determination of questions of fact by one of the following County Directors: Director of Public Works, Director of Utilities and Solid Waste Management, Finance Director or Director of Management Services. The County Manager, in his sole discretion, shall select one of these Directors to make this determination. The decision of the Director or other official is subject to review on the record by the Circuit Court for Frederick County.
On February 2, 2012, pursuant to this provision, the County appointed Kevin Demosky, the Director of the Frederick County Division of Utilities and Solid Waste Management, to serve as the hearing officer in this dispute (the “Hearing Officer”). 572 B. The Hearing Officer’s Review The Hearing Officer heard opening arguments and visited the Project Site on February 10, 2012, held evidentiary hearings on March 2 and 13, and accepted written briefs on April 5. On May 1, he issued a written decision granting in part and denying in part Ross’s claim for an equitable adjustment of the Contract price. The summary of the Hearing Officer’s findings, as provided by the circuit court, is helpful here: The Agency[ 4 ] concluded, in its Final Decision, that the rock encountered by Ross during the excavation did not amount to a materially different site condition pursuant to CPA-05 of the Contract. The Agency reasoned that Ross should have been on notice prior to the excavation that it would encounter rock at the site of the excavation, but did not conduct a proper site inspection prior to its bid.
The Agency explained that it found GP-2.04 of the Contract relevant, which waives liability of the State for the Contractor’s interpretations of information in the Contract. The Agency decided that Ross was on notice of the rock, which was visible at the site of the project. The Agency explained that the testimony demonstrated that Ross’[s] agents made at least four pre-bid site inspections, and that “[t]he possibility of hard rock was clearly visible during a pre-bid site inspection.” The Agency recognized that the soil borings provided as part of the contract did constitute a softer soil than Ross eventually encountered, but explained that “pre-construction photos in evidence suggest a sharply plunging rock stratum that would have been apparent to Ross, but which could have easily been not encountered [by the company that performed the pre-bid soil boring].” The Agency also explained that Ross was on notice that other contractors were anticipating encountering rock during the project. Specifically, the Agency referenced what has been designated as Question 19 for pre-bid hearing where the County fielded questions from bidding contrac 573 tors about the project; the Transcript of this hearing is attached to the Contract as Addendum 1.
The Agency explained, “Addendum 1 clearly indicates that other bidders were aware they would encounter rock in excavating Class 3 excavation work on the site. Addendum 1 also put all bidders, like Ross that did not attend the pre-bid meeting, on notice that they would likely encounter rock.” The Agency explained further, “... there is no way that I can disregard the notice of potential rock provided by Addendum 1 that is part of the Contract nor can I disregard the obvious and visible rock ledge that should have been addressed during a pre-bid site inspection.” The Agency explained that Ross’[s] lack of addressing the “obvious and visible rock ledge” resulted in its eventual low bid price: “Further, I find the Class 3 excavation bid comparison introduced by the County to be relevant to the issue of what a reasonable contractor bidding this Bridge project should have expected. The comparison of Class 3 excavation reflects that while Ross bid $16.00 per cubic yard (“CY”) for Class 3 excavation, the second and third lowest overall bidders bid 67.00 and 35.00 per CY respectively for Class 3 excavation (4.2 times and 2.2 times Ross’[s] bid respectively).” The Agency reasoned that “it would be inequitable to allow Ross — which should have expected to encounter hard rock — to low bid the Class 3 excavation as Ross did ... only to receive additional compensation through a differing site condition claim.” The Agency concluded that Ross misread the information at the site and in the contract, and that the State should and could not be liable for Ross’fs] error pursuant to GP-2.04 of the Contract. (Emphases added.) In granting part of Ross’s equitable adjustment claim, the Hearing Officer found that Ross was entitled to additional compensation in the amount of $31,946.41 for the pause in the project to investigate the subsurface conditions.
But the Hearing Officer denied Ross any additional compensation for the excavation of the hard rock material. 574 C. The Circuit Court’s Review On May 16, 2012, Ross filed a “Petition for Judicial Review of Agency Decision” in the Circuit Court for Frederick County. 5 The circuit court heard arguments on April 15, 2013 and entered an Opinion and Order on June 5, 2013. The court concluded that although “soil boring logs B-3 and B-4 ... demonstrate a soft subsurface material,” it agreed with the Hearing Officer’s finding “that evidence in the record supports the conclusion that Ross was aware of the possible existence of subsurface rock at the site of Abutment B.” Consequently, the court affirmed the Hearing Officer’s decision that Ross did not encounter a materially different site condition. Ross filed a notice of appeal on June 26, 2013.
II
DISCUSSION Ross raises one question for our review: did the Hearing Officer err in finding that Ross was not entitled to the full amount of its equitable adjustment claim? The County moved to dismiss, arguing that this Court lacked jurisdiction to hear Ross’s appeal. As we explain, the County is correct — Ross had no right of appeal from the circuit court judgment. 575 A. Ross’s Appeal To This Court Requires Statutory Authorization. “ ‘It is an often stated principle of Maryland law that appellate jurisdiction, except as constitutionally authorized, is determined entirely by statute, and that, therefore, a right of appeal must be legislatively granted.’ ” Prince George’s Cnty. v. Beretta U.S.A. Corp., 358 Md. 166, 173 , 747 A.2d 647 (2000) (quoting Gisriel v. Ocean City Bd. of Supervisors of Elections, 345 Md. 477, 485 , 693 A.2d 757 (1997)); see also Madison Park N. Apartments, Ltd. P’ship v. Comm’r of Hous. & Cmty. Dev., 211 Md.App. 676, 690 , 66 A.3d 93 (2013) dismissed, 439 Md. 327 , 96 A.3d 143 (2014).
As a result, Ross’s ability to appeal to this Court depends on whether that right exists under the Maryland Code. See Beretta, 358 Md. at 173-74 , 747 A.2d 647 ; Gisriel, 345 Md. at 485 , 693 A.2d 757 ; Madison Park, 211 Md.App. at 690 , 66 A.3d 93 . If no statutory authorization exists, “this Court does not have jurisdiction,” and “we must dismiss the case sua sponte.” Madison Park, 211 Md.App. at 690 , 66 A.3d 93 (citing Miller & Smith at Quercus, LLC v. Casey PMN, LLC, 412 Md. 230, 240 , 987 A.2d 1 (2010); Beretta, 358 Md. at 174 , 747 A.2d 647 ). In general, Md. Code (1974, 2013 Repl.
Vol.), § 12-301 of the Courts & Judicial Proceedings Article (“CJ”), permits this Court to hear appeals from final judgments of the circuit courts in the exercise of original, special, limited, or statutory jurisdiction: Except as provided in [CJ] § 12-302 of this subtitle, a party may appeal from a final judgment entered in a civil or criminal case by a circuit court. The right of appeal exists from a final judgment entered by a court in the exercise of original, special, limited, statutory jurisdiction, unless in a particular case the right of appeal is expressly denied by law. CJ § 12-301 (emphasis added). However, a right to appeal under CJ § 12-301 does not exist if CJ § 12-302(a) applies instead.
CJ § 12-302(a) applies to “an appeal from a final judgment of a court made in the exercise of appellate jurisdic 576 tion in reviewing the decision of ... an administrative agency.” CJ § 12-302(a) (emphasis added); see also Beretta, 358 Md. at 175 , 747 A.2d 647 ; Gisriel, 345 Md. at 486 , 693 A.2d 757 ; Madison Park, 211 Md.App. at 690 , 66 A.3d 93 . A circuit court exercises “appellate jurisdiction” when it reviews an administrative agency’s decision pursuant to statutory authorization. Gisriel, 345 Md. at 492 , 693 A.2d 757 ; see also Rogers v. Eastport Yachting Ctr., LLC, 408 Md. 722, 733-34 , 971 A.2d 322 (2009); Dvorak v. Anne Arundel Cnty. Ethics Comm’n, 400 Md. 446, 452-53 , 929 A.2d 185 (2007).
And when a circuit court reviews a decision of an administrative agency pursuant
This is a preview of Ross Contracting, Inc. v. Frederick County. About 50% of the opinion remains. Read the complete opinion in RecordCite.