Gables Constr., Inc. v. Red Coats, Inc.

241 Md. App. 1 (2019) · Maryland Court of Special Appeals
Maryland Court of Special AppealsDisposition: Aff'd in partWright, J.✓ Good law
HoldingIn the overnight hours of March 31-April 1, 2014, a fire destroyed a nearly completed 139-unit apartment building (Building G) under construction by GCI, causing over $22.15 million in damages.

Wright, J. This appeal presents a question of first impression in Maryland: whether, and under what circumstances, a contractual waiver can shield a contracting party from both third-party contribution and direct liability, in addition to other issues. We shall affirm the Circuit Court for Montgomery County's rulings and hold that a contractual waiver of subrogation does not bar contribution under the Maryland Uniform Contribution Among Joint Tort-Feasors Act ("UCATA"), but part ways with the jury verdict and hold that the contractual waiver in the Vendor Services Agreement ("VSA") and the settlement agreement and release controls the relationship between appellant, Gables Construction ("GCI"), and the appellees, Red Coats, Inc./Admiral ("Red Coats"), appellee, a security and fire watch company. In the overnight hours between March 31, 2014, and April 1, 2014, a fire damaged a 139-unit apartment building (the "Project") that was nearing completion. The building sustained damages in excess of $ 22,150,000.00.

Due to the fire, Upper Rock, Inc. ("Upper Rock"), the Project's owner, sued Red Coats, a security and fire watch company for gross negligence and breach of contract. In turn, Red Coats filed a third-party claim against GCI, the general contractor, seeking contribution under the UCATA in the circuit court. GCI responded by filing a Motion for Summary Judgment, which proved unsuccessful. After a hearing on April 1, 2016, the circuit court found that a waiver of subrogation involved in a contract between GCI and Upper Rock limited any indemnification claims, but did not limit GCI's liability for contribution.

A jury found that GCI was a joint-tortfeasor which was liable for damages, and the court awarded $ 7,000,000.00 to Red Coats, half of the damages owed to Upper Rock. GCI timely appealed and presents the following questions for our review: I. Whether the judgment should be reversed because GCI is not a "joint tortfeasor" under the UCATA.

II

Whether the judgment should be reduced because Red Coats contractually waived claims against [GCI] to the extent covered by insurance.

III

Whether the trial court erred when it entered partial summary judgment on the issue of [GCI's] negligence.

IV

Whether the trial court erred in giving ambiguous, misleading, and confusing answers to questions asked by the deliberating jury. V. Whether the trial court erred in granting the motions for judgment made against [GCI] by Retana Contractors and Rosa's Painting.

VI

Whether the trial court erred in declining to give the superseding cause instruction. We answer question II in the affirmative and question I, III, IV, V, and VI in the negative and remand for proceedings consistent with this opinion. For the reasons to follow, we will affirm in part and reverse in part the circuit court's judgments. FACTUAL AND PROCEDURAL BACKGROUND The Prime Contract In 2012, Upper Rock and GCI entered into a Document A102-2007 Standard Form of Agreement Between Owner and Contractor Contract (the "Prime Contract") to govern the construction of a complex, which included Building G, a 139-unit apartment building.

The Prime Contract listed Upper Rock as the Owner and GCI as the Contractor. 1 Section 3.18.1 of the General Conditions of the Prime Contract contained an indemnification provision which read: To the full extent permitted by law the Contractor shall indemnify and hold harmless the Owner, Architect, Architect's consultants, and agents and employees of any of them from and against claims, damages, losses and expenses, including but not limited to attorneys' fees, arising out of or resulting from performance of the Work, provided that such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself), but only to the extent caused by the negligent acts or omissions of the Contractor, Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss or expense is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge, or reduce other rights or obligations of indemnity which would otherwise exist as to a party or person described in this Section[.] Section 10.2 of the General Conditions which governed the safety of persons and property, stated, in relevant part: 10.2.4 When use or storage of explosives or other hazardous materials or equipment or unusual methods are necessary for execution of the Work, the Contractor shall exercise utmost care and carry on such activities under supervision of properly qualified personnel. * * * 10.2.6 The Contractor shall promptly remedy damage and loss (with respect to any damage or loss insured under property insurance required by the Contract Documents, Owner shall provide the insurance proceeds therefor to Contractor) to property referred to in Sections 10.2.1.2 and 10.2.1.3 caused in whole or in party by the Contractor, a Subcontractor, a Sub-subcontractor or anyone directly or indirectly employed by any of them, or by anyone for whose acts they may be liable and for which the Contractor is responsible under Sections 10.2.1.2 and 10.2.1.3, except damage or loss attributable to acts or omissions of the Owner or Architect or anyone directly or indirectly employed by either of them, or by anyone for whose acts either of them may be liable, and not attributable to the fault or negligence of the Contractor. The foregoing obligations of this Contractor are in addition to the Contractor's obligations under Section 3.18. Section 11.1.2 required GCI to carry different types of insurance including Workers Compensation and Employers' Liability Insurance, and General Liability Insurance. 2 Section 11.3.7 included a Waiver of Subrogation, at issue in this case.

The Waiver reads, in pertinent part: The Owner and Contractor waive all rights against (1) each other and any of their subcontractors, sub-subcontractors, agents and employees, each of the other, and (2) any of their subcontractors, sub-subcontractors and employees, for damages caused by fire or other causes of loss to the extent covered by property insurance obtained pursuant to this Section 11.4 or other property insurance applicable to the Work, except such rights as they have to proceeds of such insurance held by the Owner and Contractor. Furthermore, if and to the extent Contractor has its personal property located on or about the site which is not covered by the insurance obtained pursuant to this Section 11.3.7, the Contractor waives and releases Owner from all rights or causes of action (including rights of recovery and subrogation) resulting from any loss or damage to such other property, regardless of whether the same is insured by the Contractor and regardless of whether the cause for such damage is due to the NEGLIGENCE OF THE OWNER. The Owner or Contractor, as appropriate, shall require of the Architect, Architect's consultants, separate contractors described in Article 6, if any, and the subcontractors, sub-subcontractors, agents and employees of any of them, by appropriate agreements, written where legally required for validity, similar waivers each in favor of other parties enumerated herein. The policies shall provide such waivers of subrogation by endorsement or otherwise.

(Emphasis in original). Notwithstanding anything to the contrary herein contained, in the event that either Owner or Contractor ("First Party") incurs a loss by fire or other casualty, which fire or other casualty shall have been caused in whole or in party by the negligence or acts or omissions of the other party or the other party's agents, contractors, employees or servants, then to the extent that the First Party is compensated by the Builder's Risk Insurance Coverage obtained pursuant to Section 11.3 or any other property insurance of the First Party applicable to the Project, then the First Party (for itself and its successors and assigns) hereby waives and releases any claim that it might have against the other party and no party shall have any rights against either Owner or Contractor by reason of any fire or casualty damage either by subrogation or assignment. The VSA between Gables Residential Services, Inc. ("GRSI") and Red Coats Gables Residential Services Incorporated ("GRSI"), the 100% owner of GCI, contracted with Red Coats, for the provision of fire watch and security services for the Project. This contract included a 2-page VSA and a 1-page Extra Coverage/Temporary Insurance Request Form.

The VSA provided, in relevant part: Vendors providing any type of good and/or service that require their company to send a representative to the apartment community must have a current certificate of insurance on file with Compliance Depot for general liability, auto liability, excess liability if applicable, and workers' compensation. All coverage shall be primary and non-contributory. The following parties must be added to the general liability policy as an additional insured as their interests may appear in regard to work performed by Vendor: GABLES RESIDENTIAL SERVICES, INC., ITS PARENT, MEMBERS, SUBSIDIARIES AND AFFILIATED COMPANIES; AND THEIR PARTNERS, JOINT VENTURERS; AND THEIR RESPECTIVE DIRECTORS, OFFICERS, EMPLOYEES, AGENTS AND REPRESENTATIVES. A waiver of subrogation shall apply in favor of the aforementioned parties on all policies as permitted by law.

(Internal quotations omitted). The Extra Coverage/Temporary Request Form, signed by Christopher Hauska, GCI's project manager, indicated that the Red Coats officer was to "patrol the property to watch for unauthorized individuals coming on the property. No one should be on the property outside of work hours without prior authorization from Gables personnel." The form also listed GCI's point of contact as Oscar Ancheta, GCI's assistant superintendent for the Project. As adduced at trial, Red Coats services were necessary because GCI had previously had a Bobcat 3 stolen from the premises.

The Fire at Building G In the overnight hours between March 31, 2014, and April 1, 2014, Building G caught fire, thirty days short of certification for occupancy. After the fire, several parties came to inspect the scene including a state trooper, Traveler's Insurance, and various causation experts, some of whom testified at trial. The parties dispute who placed the mushroom heaters in the hallway that led to the fire. 4 Upper Rock filed a complaint with the Circuit Court for Montgomery County against Red Coats and Tamika Shelton, Red Coats' security guard on duty the night of the incident, seeking damages for $ 22,150,000.00, and alleging that both Red Coats and Shelton were the proximate and negligent cause of the building's destruction. Upper Rock did not name GCI as a party to the complaint.

In the settlement of that legal action, Red Coats paid $ 14 million to Upper Rock, $ 4 million of which it paid out of pocket, with the remaining $ 10 million paid by its insurer, and conceded that it was a joint tortfeasor. Red Coats' Third-Party Contribution Claim After settling with Upper Rock, Red Coats and Shelton filed an Amended Third-Party Complaint against GCI, Retana Contractors, LLC ("Retana"), Rosa's Painting ("Rosa's") and C & R Carpentry ("C & R") 5 (collectively "the third-party defendants") alleging that were Red Coats and Shelton found to be liable to Upper Rock, the third-party defendants were liable to Red Coats by way of contribution or indemnification. In response, GCI moved for summary judgment and argued that the VSA insulated GCI, as a named additional insured, from Red Coats' third-party complaint. GCI also denied joint tortfeasor status, averring that, at a minimum, Red Coats would need to plead that GCI was liable to Upper Rock for the same damages Upper Rock pursued against Red Coats.

At trial, Red Coats moved for partial summary judgment as to GCI's negligence. GCI conceded its breach of the standard of care by way of the testimony of Richard Kreimborg, its withdrawn standard of care expert. The circuit court questioned "[w]here's the testimony that says that your client did not breach the standard of care[,]" and asked "what's the factual question?" Counsel for GCI pointed to the fact that the testimony of an independent consultant, Donald Greene, infra , established that GCI's actions were reasonable related to the heaters and claimed that Red Coats did not have sufficient evidence establishing that GCI breached the standard of care. The court found that Kreimborg's testimony was "an admission of a party opponent," and that there was no genuine dispute of material fact regarding GCI's breach of the standard of care pursuant to Md. Rule 2-501.

Testimony at Trial Blaine Wilson, the Executive Vice President for Corporate Human Resources for Red Coats, testified that Red Coats contracted with GRSI to "provide services during evening hours, approximately 5:00 p.m. to 6:00 a.m." Wilson testified that, initially, Red Coats was hired to patrol the exterior of the worksite to prevent thefts. Wilson confirmed that Shelton was on duty the evening the incident occurred, and that she performed her patrols as required under the contract. Wilson's testimony discredited GCI's testimony that one of its employees walked Shelton through Building G to show her where to patrol. In addition, Wilson testified that GCI never provided training for Shelton and never informed Red Coats that temporary mushroom heaters were in use.

Finally, Wilson confirmed that Red Coats settled its suit with Upper Rock and paid $ 4 million out of pocket. On cross-examination, Wilson stated that it was a policy of Red Coats that security officers could not go into buildings that were under construction. Shelton testified that she had been on-duty the night in question, but that GCI never informed her that there were temporary mushroom heaters being used at the site. She also testified that GCI never ordered her to go inside the building.

On cross-examination, Shelton testified that she received training on fire watch from Red Coats and that the "contractors were still there" when she arrived on the job. William Olin, a fire investigator, testified that he investigated the causes and origin of the fire, but was unable to determine whether the fire was caused by electrical wiring. Michael Newberry, a Fire Investigator for Atlantic Fire, testified that it was his opinion that the cause of the fire was the mushroom heaters owned by GCI. Newberry also testified that the hallway was five feet and six inches wide and that the heaters required four feet of space between the nearest combustible.

Newberry's testimony also established that four heaters were found on the fourth floor of Building G. Brent Leisenring, a civil engineer with Robson Forensic, Inc., could not identify who placed the mushroom heater in the hallway but testified that GCI breached the relevant standard of care by failing to: 1. Perform and prepare a job hazard analysis and fire protection plan per [the National Fire Protection Association] ("NFPA") 241 [§§ 5.2.2 and 5.2.3]. 2. Properly coordinate their Project specific requirements for fire watch, which should have been addressed with Red Coats. 3. Ensure that the temporary heating equipment was utilized in compliance with the equipment's operating instructions. 4.

Train their own workers pursuant to [Occupational Safety and Health Administration] ("OSHA"). 5. Place the heater in the proper place. 6. Ensure that [Red Coats'] workers with responsibility for fire watch were properly trained Jan Inguiagiato, a construction worker, testified that Travelers Insurance contacted his firm to assist with the loss after the fire. Inguiagiato physically inspected the building to ascertain "what work had been put into place at the time of the fire." He also testified that Red Coats' $ 14 million payout was "reasonable." Mark Nelson, a forensic engineer, testified that a mushroom heater caused the damage to the building, and that a manual said that clearance from the top of the heater to the ceiling required a clearance of five feet and ten inches.

Christopher Graham, an electrical engineer, testified that he could not find an electrical cause for the fire. Next, the circuit court heard testimony from Retana employee, Julio Retana. Retana testified that none of the painters brought the mushroom heaters to the worksite and stated "I suppose somebody who worked for [GCI]" brought the heaters to Building G. On June 5, 2017, the parties notified the circuit court that Red Coats had resolved its claims with Retana, Rosa's, and C & R, leaving GCI as the sole non-settling defendant. GCI's counsel preserved its objection that any duty GCI may have had was contractual in nature, as opposed to a duty arising from tort, and that it was precluded from having a duty because of the waiver of subrogation.

GCI further noted that it was precluded from a direct negligence action because of the VSA. At this point, GCI moved for judgment which was denied. The court stated the following: I am persuaded that [GCI] had, and the jury could find, an independent tort duty to Upper Rock arising out of, among other things, Section 324(a), the Restatement (Second) of Torts ... It is obvious to me that you had four mushroom heaters with no training, no supervision, used against their protocols, against the instruction manual, it [is] an explosion waiting to happen, and the fact that nobody was hurt is a great thing, but it doesn't take [GCI] off the hook.

Bill Stewart, GRSI's Director of Construction, testified that GCI hired Red Coats to provide security and fire watch services on the site after GCI had to fire its previous vendor. Stewart testified that GCI was a subsidiary of GRSI and testified as to the corporate structure of GRSI. When questioned about whether GCI had a written policy regarding fire watch, Stewart said "I don't believe so." Lastly, Stewart testified that it was Hauska's responsibility to review the owner's manual for the mushroom heaters to determine how to safely operate the heaters. On cross-examination, Stewart testified that Oscar Ancheta, GCI's Assistant for the Project, Mario Branco, the Project superintendent, and Hauska handled fire watch.

Stewart also noted that he was not aware of any training programs that GCI had regarding the use of temporary heating equipment, and that it was Ancheta's responsibility to walk the job site to make sure no hazardous conditions were present. On June 6, 2017, the circuit court heard testimony from Branco, Jorgen Punda, GRSI's Regional Vice President of Investments, 6 and Donald Greene. Branco testified that all GCI employees were aware that the mushroom heaters were not to be used in a confined space, that the heaters were to be turned off every night before everyone left the construction site, and that these instructions would have been communicated to the foremen of the subcontractors. Branco testified that he did not see the mushroom heaters in the hallway, and that it would have been a violation of GCI's policy if the heaters remained operational after hours.

Greene testified that "fire watch" is "a security patrol to identify potential fire hazards which could be dangerous to property and persons." After the circuit court heard testimony and dismissed the jury, Retana moved for judgment against GCI. 7 Retana argued that the contract between GCI and Upper Rock contained a waiver of subrogation, arguing that it was in privity with GCI as a sub subcontractor. Next, Retana argued that GCI had not met its burden in proving a duty on behalf of Retana to turn the mushroom heaters off at the end of the day because the contract does not explicitly mention heaters, thus there is no duty. Retana pointed to the testimony of Stewart, who testified that GCI oversaw the heaters and was in charge of distributing manuals to subcontractors and sub-subcontractors. Retana also noted the testimony of Retana employee, Julio Retana, who testified that he never received instructions or direction related to the mushroom heaters.

Lastly, Retana pointed to the testimony of Hauska, who testified that he "had no idea" who operated the heaters. In summary, Retana claimed that there was no evidence that either Retana or Rosa's had a duty to turn the heaters off at the end of the day. According to Retana, the only reasonable explanation for the fire is that the heaters were turned on after both Retana and Rosa's had left for the day. Regarding the contribution claim, Retana's counsel argued that "[c]ontribution is the same argument with the added wrinkle of the waiver of subrogation which bars that claim." Rosa's also moved for judgment, adopting Retana's arguments.

Rosa's argued that there was no evidence showing who was the last to leave. What was known, according to Rosa's, was that GCI's protocol was to turn off the heaters at 6:00 p.m. Lastly, Rosa's argued that it was a borrowed employer of Retana. GCI opposed Retana and Rosa's Motions for Judgment but agreed that the contract between GCI and Upper Rock contained a waiver of subrogation. 8 On the breach of contract claim, GCI conceded that there was nothing in the job safety manual or the job procedures manual stating that subcontractors were responsible for the heaters.

As the circuit court questioned GCI on its defense, the following colloquy ensued: THE COURT: Where is there anywhere in any writing that's in evidence, anything at all, about whose job it was or what the requirements were, if you will, about the operation or maintenance of the mushroom heater. MS. RUSSELL: I think, as the Court is aware, the evidence that has been presented, both orally and in writing, there is no such memo. There is no such line that says, specifically, has specifically anything to do with the handling of the heaters.

But there are provisions that talk about fire safety, combustibles, things like that, that we believe are applicable in this case. THE COURT: Well, you agree, I take it that your client owned the heaters, right? MS. RUSSELL: I do.

THE COURT: And do you also agree that if your client is the owner of a potentially dangerous device that before they allow somebody to use it, they have to give them some kind of training or safety instruction? The circuit court granted both Retana's and Rosa's Motions for Judgment based on their counsel's arguments and because GCI presented "no evidence, at all, from which a reasonable jury could find a breach of contract, written or oral." Next, the circuit court addressed C & R's motion for judgment. Counsel for C & R argued that there was an absence of evidence related to "who took the heater and put it into that position in that hallway[.]" The court granted C & R's motion because, again, there was no evidence suggesting a connection between C & R and the heaters. Lastly, Red Coats moved for judgment against GCI for the remaining issue on its contribution claim - causation.

Red Coats argued that the circuit court's grant of Red Coats' motion for partial summary judgment established that GCI breached its duty by putting the mushroom heaters in the hallway. The court chose to send the issue of causation to the jury. Jury Notes During its deliberation, the jury sent five notes to the court: 1. Does the waiver of subrogation in the vendor services agreement only apply to insurance coverage/claims, that is specifically, $ 10 million?

( [Red Coats'] insurance payout) [?] 2. Is [GCI] a subsidiary/affiliate of [GRSI]? 3. How many pages are included in the contract between [Red Coats] and Gables (RC Exhibits 4 and 5)? 4. Is [the VSA] the only agreement/contract between [Red Coats] and [GCI] (Exhibits -RC - 4 and 5)? 5.

How do we decide Question 3: a. Can we base the amount on assignment of blame or b. Does it need to be a percentage of the full settlement ($ 14 million) or only the insurance payout ($ 10 million) or the [Red Coats] contribution ($ 4 million)? Pertinent is the circuit court's supplement to its previous instructions on the waiver of subrogation issue as follows: [GCI] contends that [Red Coats] and Ms. Shelton may not recover for any monies that they paid to Upper Rock against it by reason of a waiver of subrogation. [GCI] contends that there is a contract to that effect and that this contract bars any contribution claim. [Red Coats] and Ms. Shelton disagree.

They contend that the parties did not contract to waive subrogation, either in whole or in part. That is, either for any money paid on their behalf to Upper Rock by an insurance carrier or any money they paid directly to Upper Rock. I remind you that a waiver of subrogation is (1) an affirmative defense on which (2) [GCI] bears the burden of proof by (3) a preponderance of the evidence. The party with the burden of proof must prove that something is more likely so than not so.

If you believe that the evidence on a question of fact that you must decide is evenly balanced, then your finding on that issue must be against the party who has the burden of proving it. By way of special verdict sheet and in response to the question "[w]as the fire that occurred on the evening of March 31-April 1, 2014, a direct result and a foreseeable consequence of [GCI's] negligence," the jury responded "yes." In response to the question "[i]s [Red Coats] precluded from recovering for contribution against [GCI] based upon a contractual waiver of subrogation, in whole or in part," the jury answered "no." Following the jury's verdict, the circuit court entered the following notices of judgment: ... 6. A partial verdict in favor of [Red Coats] against [GCI] as to negligence. 7. A verdict in favor of [Red Coats] against [GCI], as to Red Coats's preclusion from recovering for partial or total contribution against [GCI] based upon a contractual waiver of subrogation. 8.

A judgment against [GCI] in the amount of seven million dollars ($ 7,000,000.00). Unhappy with the outcome of the trial, GCI timely filed an appeal on July 3, 2017. Additional facts will be included as necessary below. DISCUSSION I. Preservation At the outset, Red Coats asserts that GCI did not specify the ruling it appeals related to its joint tortfeasor status.

Red Coats further argues that GCI is precluded from appellate review because it only raised the issue of joint tortfeasor status in a pre-trial judgment motion and by moving for judgment after Red Coats closed its case-in-chief. The record reflects that GCI moved to appeal the circuit court's judgment against it for a one half pro rata share of Red Coats' settlement with Upper Rock. This judgment was based upon the jury finding that Red Coats was not precluded, either in whole or in part, from recovering contribution from GCI based on a waiver of subrogation. Thus, to properly preserve this claim for appellate review, GCI would have had to preserve in the record its objections to whether or not Red Coats was precluded by the waiver of subrogation in the Prime Contract, which it did.

In fact, GCI claimed several times in pleadings and at trial that it was not a joint tortfeasor. See Collins/Snoops Associates, Inc. v. CJF , LLC , 190 Md. App. 146 , 165-66, 988 A.2d 49 , cert. denied , 414 Md. 331 , 995 A.2d 297 (2010). Contrary to Red Coats' assertions, this claim continued after the court ruled in partial summary judgment that GCI breached its duty. Therefore, we hold that this issue was preserved.

History of UCATA in Maryland At common law and before the enactment of the UCATA in 1941, "a statutory right of contribution among joint tortfeasors ... did not exist[.]" Central GMC, Inc. v. Helms , 303 Md. 266 , 276, 492 A.2d 1313 (1985). As early as the 1700s, courts in England did not allow a joint tortfeasor to seek contribution from additional liable parties. Montgomery County v. Valk Mfg. Co. , 317 Md. 185 , 189, 562 A.2d 1246 (1989) (citing Merryweather v. Nixan , 8 Term.

Rep. 186, 101 Eng. Rep. 1337 (1799) ). Sister courts in the United States, too, barred contribution in cases of willful misconduct. Valk , 317 Md. at 189 , 562 A.2d 1246 .

While neither of these early courts addressed contribution in cases of negligence, American courts eventually extended bars to contribution in that area. Id. This change was widely criticized: There is obvious lack of sense and justice in a rule which permits the entire burden of a loss, for which two defendants were equally, unintentionally responsible, to be shouldered onto one alone, according to the accident of a successful levy of execution, the existence of liability insurance, the plaintiff's whim or spite, or the plaintiff's collusion with the other wrongdoer, while the latter goes scot free. Valk , 317 Md. at 189 , 562 A.2d 1246 (citations omitted).

Even if two or more parties were liable for an injured person's harm, only one party would bear the brunt of financial liability. Even if that burdened party knew an additional party was just as responsible for the harm, it could not seek contribution. In simpler terms, this meant that if an injured party, A, sued a tortfeasor, B, B could never recover money from C, even if C was also responsible for A's injury. This gave injured parties the power to cherry-pick which tortfeasor it would sue, forcing the weight of financial responsibility on one party alone.

Valk , 317 Md. at 189 -90 , 562 A.2d 1246 . Due to this conundrum, tortfeasors were encouraged to settle for less than the full amount of damages because of the "fear of each that unless he settles he may have to bear alone the full weight of the verdict." Fleming James, Jr., Contribution Among Joint Tortfeasors: A Pragmatic Criticism , 54 Harv. L.Rev. 1156 , 1161 (1941). The UCATA was promulgated in 1939 by the American Law Institute and the National Conference of Commissioners on Uniform Laws to address this inherent unfairness.

Prefatory Note, Handbook of the National Conference of Commissioners on Uniform State Laws and Proceedings of the Forty-Ninth Annual Conference 240-41 (1939). The General Assembly adopted the UCATA, based on this national model in 1941. Id. at 241 . After its adoption, the Court of Appeals stated: "The primary purpose of the [UCATA] was to create a right of contribution among joint tortfeasors which did not exist at common law ... and to establish a procedure whereby that right might be made effective in practice." Baltimore Transit Co. v. State ex rel.

Schriefer , 183 Md. 674 , 679, 39 A.2d 858 (1944). 9 Under UCATA, one liable party no longer bears the burden of damages alone as that party now has a statutory right to seek contribution from other, liable parties. In place of the "release of one releases all" standard at common law, the UCATA provides that a release of one joint tortfeasor does not relieve the liability of other joint tortfeasors, but reduces the judgment against them by either the consideration paid for the release or an amount or proportion provided in the release, whichever is greater. This statutory right, however, has its limitations. Per the UCATA, one tortfeasor can only sue another if "there is a common liability to an injured person in tort." Valk , 317 Md. at 192 , 562 A.2d 1246 .

A distinction exists, though, between common liability and joint negligence. The Minnesota Supreme Court has noted, "[c]ontribution rests on common liability, not on joint negligence or joint tort. Common liability exists when two or more actors are liable to an injured party for the same damages, even though their liability may rest on different grounds." Pautz v. Cal-Ros, Inc ., 340 N.W.2d 338 , 339 (Minn. 1983) (citation omitted). GCI is a Joint Tortfeasor under the UCATA For the purposes of this limited discussion of GCI's joint tortfeasor status, we have put aside the effect of the waiver of subrogation.

That conversation will follow. GCI argues that the waiver of subrogation in the Prime Contract precludes Red Coats from recovery under UCATA. Primarily, GCI advances that because Red Coats entered into a settlement with Upper Rock, it can only receive contribution from a person with whom it is "jointly or severally liable in tort[.]" See Md. Code (1973, 2013 Repl. Vol.), Courts & Judicial Proceedings Article ("CJP") § 3-1401(c).

GCI argues that it is not a party that was "jointly or severally liable in tort" for the harm to Upper Rock due to the waiver of subrogation in the Prime Contract. Red Coats responds that GCI is a joint tortfeasor under UCATA because the jury "adjudicated GCI to be a joint tortfeasor" by rendering a verdict that GCI's negligence was a proximate cause of the fire that destroyed Building G. In responding to GCI's claim that it is barred by the waiver of subrogation in the Prime Contract, Red Coats responds that neither it nor Shelton were a party to the contract. Further, Red Coats argues that if we hold that the waiver of subrogation serves as a contractual shield to UCATA, we will upset the core of UCATA. That is, the "inherent injustice" of a liable party escaping scot-free, even in cases of substantial bodily harm or death.

The UCATA defines joint tortfeasors as: "two or more persons jointly or severally liable in tort for the same injury to person or property, whether or not judgment has been recovered against all or some of them." CJP § 3-1401(c). A party can be defined as a joint tortfeasor through its own admission or by judicial determination. An injured person is defined as "any person having a claim in tort for injury to person or property." CJP § 3-1401(b). Maryland precedent provides that a party may qualify as a joint tortfeasor upon adjudication as liable or upon conceding its own liability.

See Martinez v. Lopez , 300 Md. 91 , 94-95, 476 A.2d 197 (1984) (establishing that a party in the case became a joint tortfeasor when it signed a release reading "for the purposes of the aforegoing Release" [the parties] are to be consider joint tortfeasors within the meaning of the [Md. Act]"). However, UCATA "does not specify the test of liability." Swigert v. Welk , 213 Md. 613 , 619, 133 A.2d 428 (1957). Without an admission or adjudication of liability, a party who enters into a release is deemed a volunteer, not a joint tortfeasor. Scapa Dryer Fabrics, Inc. v. Saville , 418 Md. 496 , 529-30, 16 A.3d 159 (2011).

On its special verdict sheet and in response to the question "[w]as the fire that occurred on the evening of March 31-April 1, 2014, a direct result and a foreseeable consequence of GCI's negligence?" the jury responded "yes." In addition, the circuit court entered summary judgment on the issue of GCI's negligence related to the heaters, which testimony adduced was the cause of the fire to Building G. Therefore, for the purposes of this appeal, both the court and the jury determined that GCI was a joint tortfeasor with Red Coats for the purposes of UCATA, and thus, we now turn to whether Red Coats can seek contribution from GCI. The Waiver of Subrogation does not bar recovery under UCATA GCI presents an issue of first impression for our review: whether a waiver of subrogation can serve as a contractual shield that both prevents direct liability to an injured party and bars any third-party contribution claims under UCATA . As we will discuss below, the waiver of subrogation, in this case, does not waive GCI's direct liability to Upper Rock, and therefore, cannot serve as a complete bar to recovery pursuant to UCATA. 10 As we will discuss, Maryland courts have recognized bars to contribution under UCATA, including family immunity, spousal immunity, and contributory negligence. GCI argues that the waiver of subrogation in the Prime Contract is like these other bars to recovery and argues that the Court of Appeals' decision in Valk , 317 Md. at 199 -200 , 562 A.2d 1246 , is dispositive.

Red Coats counters that Parler & Wobber v. Miles & Stockbridge , 359 Md. 671 , 756 A.2d 526 (2000), controls. We agree with Red Coats and hold that the waiver of subrogation by contract in the Prime Contract cannot serve as a bar to contribution under UCATA. The waiver of subrogation is only germane to the contract and does not spring from the relationship of the parties or the tortious conduct. i. Contributory Negligence as a bar to contribution under the UCATA The Court of Appeals first addressed the issue of joint tortfeasor contribution in cases of contributory negligence in Valk , 317 Md. at 186 -87 , 562 A.2d 1246 .

In Valk , the Court addressed the issue of whether a manufacturer could recover from the plow's user some of the money it paid to the plaintiffs, even if the plaintiffs could not have held the plow's user liable due to contributory negligence. Id. at 186 , 562 A.2d 1246 . Prior to 1982, Montgomery County purchased a snow plow made by the Valk Manufacturing Company and installed it on one of its trucks. Id. at 187 , 562 A.2d 1246 .

In December 1982, "the County drove the truck with the plow device, but without the plow blade." Id. When it was without its blade, the steel plow arm became a deadly device, described as a "battering ram." Id. Dr. Rangaswamy, the decedent, was driving in Montgomery County when his car collided with the County's plow truck. Valk , 317 Md. at 187 , 562 A.2d 1246 .

In fact, Dr. Rangaswamy had pulled onto the road directly in front of the oncoming truck. Id. Due to the collision, the steel plow arm of the snow plow penetrated the driver's side window. Id.

The doctor "suffered puncture wounds to the left side of his skull and chest injuries" and died. Id. Dr. Rangaswamy's wife and son brought a wrongful death action against the County and a strict liability claim against Valk. Id.

Valk, in turn, filed a negligence cross-claim against the County for contribution. Id . The circuit court found that Dr. Rangaswamy was contributorily negligent in pulling his car into the intersection and dismissed the wife and son's claim against the County, as well as Valk's cross-claim, which Valk would later appeal. Valk , 317 Md. at 187 -88 , 562 A.2d 1246 .

Therefore, the only thing left to decide was the strict liability claim against Valk. Id. at 188 , 562 A.2d 1246 . A jury found that Valk was liable for creating a "defective and unreasonably dangerous snow plow design." Id . at 188, 562 A.2d 1246 . Valk filed an appeal challenging the dismissal of Valk's cross-claim against the County for contribution.

On appeal the Court of Appeals considered the meaning of the terms "liable in tort" and "common liability" in the UCATA. Specifically, it addressed the terms in the context of interspousal immunity, worker's compensation, and contributory negligence. Id. at 191-92 , 562 A.2d 1246 . The Court first addressed Ennis v. Donovan , 222 Md. 536 , 161 A.2d 698 (1960), a case where a plaintiff sued Ennis for negligent driving.

In response, "Ennis sued the plaintiff's spouse who had been driving at the time of the accident." Valk , 317 Md. at 192 , 562 A.2d 1246 . The Court found that UCATA was "only applicable to a situation where there is a common liability to an injured person in tort." Ennis , 222 Md. at 540 , 161 A.2d 698 . Next, the Court discussed Schriefer , 183 Md. at 679 , 39 A.2d 858 . There, the Court "barred contribution where a third party defendant was an employer who had achieved immunity through compliance with the Workmen's Compensation Act." Valk , 317 Md. at 192 , 562 A.2d 1246 .

The Valk Court stated that in reaching its conclusion in Schriefer , "relied on the Commissioners' notes to the 1939 version of the UCATA." Id. at 192-93 , 562 A.2d 1246 . Those notes, relevant here, stated: The common obligation contemplated by this Act is the common liability of the tortfeasors to suffer adverse judgment at the instance of the injured person whether or not the injured person elects to impose it and 2) the Act permits contribution among all tortfeasors whom the injured party could hold liable jointly and severally for the same damage or injury .... Id. at 193 , 562 A.2d 1246 (quoting Schriefer , 183 Md. at 680 , 39 A.2d 858 ). The Valk Court then noted, "[t]hese comments clearly reflect the Act's assumption that contribution from a third party defendant is predicated on his or her direct liability to the plaintiff." Valk , 317 Md. at 193 , 562 A.2d 1246 .

Schriefer now stands for the proposition that, "there [is] no right of contribution where the injured person has no right of action against the third party defendant." Id. (quoting Stem v. Nello L. Teer Co ., 213 Md. 132 , 142, 130 A.2d 769 (1957) ). Aptly, the Court noted that immunities are "on the wane," and that courts are "reluctant to bar contribution among unintentional wrongdoers." Valk , 317 Md. at 196 , 562 A.2d 1246 . Next, the Court turned to the issue of contributory negligence as a bar to recovery stating, "[l]ike intrafamily immunity, contributory negligence bars recovery against wrongdoers." Id. at 197 , 562 A.2d 1246 .

The Court looked to cases that address contributory negligence and recovery and found that most courts bar contribution against a third party defendant who asserts the defense of contributory negligence. Id. at 198 , 562 A.2d 1246 . The Court noted that this result seemingly flowed from the "natural consequences of the debate that has raged over family immunities." Id. at 198 , 562 A.2d 1246 . The Court held that the County was not liable to the plaintiffs because contributory negligence rendered the County not "legally responsible to the plaintiff for his or her injuries." Id . at 200, 562 A.2d 1246 .

Due to the lack of liability to the plaintiff, therefore, the Court reasoned that the County was not a joint tortfeasor under the UCATA and held that the circuit court properly dismissed Valk's cross-claim for contribution against the County. Id. ii. Immunities as a bar to contribution under the UCATA The next case of considerable interest is Parler & Wobber , 359 Md. at 676 -77 , 756 A.2d 526 , which presented an issue of first impression: whether a lawyer "being sued by a former client for malpractice, could obtain contribution or indemnification from a successor lawyer stemming from the successor's malpractice or negligent misrepresentation of the same client in the same matter." Id . at 676-77, 756 A.2d 526 . On appeal, the law firm Miles & Stockbridge argued that it had a statutory right to implead Parler for contribution under the UCATA because UCATA serves to "[ensure] that the cost of injuries is distributed fairly among joint-tortfeasors[.]" Id . at 682, 756 A.2d 526 .

Parler, conversely, argued that an impleader action under UCATA would breach the attorney-client relationship by "invading the successor attorney's duty of confidentiality owed to the client and the attorney-client privilege." Id. at 683 , 756 A.2d 526 . The Court looked to the decisions of sister states that, in a reluctance to undermine the UCATA, had "refuse[d] to recognize a direct action in negligence or third party action in contribution ... for fear of the adverse impact such an action would have on the attorney-client relationship." Id . at 694, 756 A.2d 526 . The Court held that "[p]rohibiting a joint tortfeasor action in this case would open an undesirable loophole in Thomas v. Bethea , 351 Md. 513 , 718 A.2d 1187 (1998), [ 11 ] and circumvent the purpose of the UCATA." Parler , 359 Md. at 704 , 756 A.2d 526 . The Court noted that the central premise of Thomas and the UCATA is that "a party should be held accountable for damages caused by his or her negligence." Id.

The Court also indicated "[w]e think the better public policy approach is for the parties to lay their cards on the table for the fact-finder to determine the facts and allocate the loss to the proper parties, rather than granting successor counsel a shield of immunity for its alleged wrongful acts." Id. at 705 , 756 A.2d 526 . iii. The Waiver of Subrogation in the Prime Contract The waiver of subrogation in the Prime Contract is different in kind from both immunity and contributory negligence, which are bars to recovery under UCATA. Immunity and contributory negligence arise from the wrongdoing itself. See Valk , 317 Md. at 197 n.16, 562 A.2d 1246 .

By contrast, the waiver of subrogation here stems from a contractual agreement formed long before the harm occurred. In Valk , Dr. Rangaswamy's contributory negligence barred his family's recovery. That contributory negligence, attributed to the decedent, severed the direct liability to Dr. Rangaswamy's survivors that was essential to a contribution claim under UCATA. Id. at 188 , 562 A.2d 1246 .

Similarly, in Parler , the issue of impleader and attorney-client privilege was connected to the actions of an earlier attorney. In spousal immunity and intra-family immunity cases, our courts have barred contribution precisely because the family relationship severed the "common liability" to a plaintiff. In Valk , however, the Court of Appeals noted both a reluctance to carve out exceptions to UCATA and that immunities were "on the wane." Valk , 317 Md. at 196 , 562 A.2d 1246 . Waivers of subrogation, treated as contracts, are different from these historical bars to contribution.

A contract is an agreement that creates an obligation or a promise or set of promises for breach of which the law provides a remedy, or the performance of which the law recognizes as a duty. See Post v. Gillespie , 219 Md. 378 , 149 A.2d 391 (1959) ; County Com'rs for Carroll County v. Forty West Builders, Inc ., 178 Md. App. 328 , 941 A.2d 1181 (2008) ; Goldstein v. Miles , 159 Md. App. 403 , 859 A.2d 313 (2004). A "contract is binding only upon the parties to the contract and their privies." Homeseekers' Realty Co. v. Silent Automatic Sales Corp ., 163 Md. 541 , 545, 163 A. 841 (1933). Bars to contribution such as contributory negligence and family immunity are enforceable against the world at large.

By contrast, GCI's and Upper Rock's waiver of subrogation is only enforceable as to the parties to the contract and does not apply to Red Coats. As such, we hold that a contractual waiver of subrogation does not extinguish the right to contribution of a joint tortfeasor who has not bound itself to that provision of the contract. If we hold differently, contracting parties would be able to return to the pre-UCATA days. This could create a chilling effect on business relationships if the new normal is to insulate business entities from liability and contribution claims.

It is well-settled that a "contractual agreement between a plaintiff and a co-defendant cannot serve to define the liability of another co-defendant not a party to the agreement." Rivera v. Prince George's County Health Dep't , 102 Md. App. 456 , 478, 649 A.2d 1212 (1994). That determination is not ours to make, and we suspect that had the legislature intended to provide that contractual shield, it would have done so. See Valk , 317 Md. at 199 , 562 A.2d 1246 . We will not do so here today. 12 The Settlement Agreement and Release between Upper Rock and Red Coats Limits Red Coats' recovery from GCI On