Maryland case law › University of Maryland v. Maas

University of Maryland v. Maas

173 Md. 554 (1938) · Court of Appeals of Maryland
Court of Appeals of MarylandDisposition: ReversedShehan, J.✓ Good law
HoldingThe University of Maryland appealed from a judgment of $11,000 entered against it in the Superior Court of Baltimore City for breach of contract in connection with the construction of a dormitory.

Shehan, J., delivered the opinion of the Court. The Maas Construction Company sued the University of Maryland in the Superior Court of Baltimore City and recovered a judgment for $11,000 damages for breach of contract, from which the defendant appealed. The questions here presented for review of this court arise on the ruling on a demurrer to a second amended declaration, and brings into question the immunity of this university from suit by reason of its status as a governmental agency of the State, and also a question on the ruling on a prayer relating to an alleged breach of contract by the appellees, which, by their own wrong, it is claimed, precluded a recovery. The prayer was rejected on the theory that the plaintiff had not violated the terms of the contract by ceasing work in the construction of a dormitory, as provided in the contract.

The University of Maryland urged upon the lower court, as it does here, that because of the relationship it bears to the State, it was entitled to immunity from suits of this character; and, further, that all of its funds being appropriated by law for the purposes of such agency are, therefore, charged with the public trust, and it is restricted in its expenditures to legislative appropriations and to those purposes expressly designated by law, and without any inherent authority to raise money for the payment of claims against it. The questions before us are: First, is the University of Maryland, as a governmental agency, protected and immune from suits for damages unless legislative authority has been given to sue it, and has such authority been given; second, does it possess funds with which to pay the judgment if recovered against it, and if not, does this suit fail for that reason; and, third, did the construction 556 company abandon the work under the contract without legal justification or excuse? We will consider these questions in the order named, first reviewing briefly the facts. The contract in question provided for the construction of a dormitory for the University of Maryland.

Under its terms, the construction company was entitled to receive ninety per cent of the value of the work done up to the first day of the month, less the sum of such payments previously made, and this payment was to be made on or about the tenth day of the succeeding month. The architect was required to certify, on or before the tenth day of each month, the amount of the work completed. Upon the failure of the University of Maryland to pay the construction company within seven days after the certificate was issued, the appellee had the right, upon seven days’ written notice by them to the University of Maryland, to stop work and terminate the contract, and to recover from the University payment “for all work executed and any loss sustained upon any plant or materials and reasonable profits and damages.” In May, 1934, the work was commenced. A certificate, under the provisions of said contract, was issued on the 9th day of July, for $10,101.91, representing ninety per cent of the work actually done.

The construction company, on the 11th day of July, demanded of the University of Maryland the payment of this sum, and notified it, unless the payment was made in accordance with the amount certified by the architect, pursuant to the terms of the contract, on or before seven days from the date of receiving the letter, they would stop work and terminate the contract. The first difficulty between the parties grew out of a notice to the appellant, from the National Casualty Company, surety on the construction company’s bond, requesting the university to withhold payments pending arrangements or assurances whereby the money paid would be used to pay subcontractors. Dr. H. C. Byrd, then vice-president of the university, notified the appellees 557 of this request from the surety company, and suggested that they communicate with the surety company and endeavor to reach an agreement with respect to the application of payments, and, on July 17th, consent was had from the surety company that the university pay the amounts certified by the architect. On the 18th of July, the foreman of the company was advised that the money would be available for the payment at any time.

This information was given to the foreman because neither of the appellees could be found. On July 20th, counsel of the appellees was advised that the surety company had withdrawn its objection and that the money would be paid as soon as the check could be cleared through the comptroller’s office, but on the next day, the 21st of July, the construction company wrote the regents of the university as follows: “You are hereby advised that all work on said contract is being terminated as of this date, the equipment removed, and from and after this date all materials on the job are there at your risk. Our watchman will not remain on the premises after tonight.” With this exchange of communications and assertions of rights, work under the contract was finally terminated. The construction company brought this suit to recover damages for the breach of contract, and the demurrer raises the question first above mentioned.

It has been decided in University of Maryland v. Murray, 169 Md. 478 , 182 A. 590, 591 , that the University of Maryland is an arm or agency of the state government, and chapter 29 of the Laws of 1922, and the case of University of Maryland v. Coale, 165 Md. 224 , 167 A. 54 , further establish this beyond question, as well as the character of the governmental functions of this institution of learning. The decided cases here and elsewhere recognize and affirm the principle that purely governmental agencies, because of their relation to the state, are entitled to immunity from suits as is the state itself, unless the legislature has expressly authorized suits to be brought against it, but this authority to sue is not free from restrictions, even though they are not expressly 558 made by the legislature, for this court has held that suits may not be maintained unless money has been appropriated for the payment of such damages as may be awarded, or the agency itself is authorized to raise money for that purpose. In the case of State v. Rich, 126 Md. 643 , 95 A. 956 , Judge Urner, speaking for this court, said: “In view of the relation which the commission thus bears to the State, it is entitled, in a case like the present, to the benefit of the state’s immunity from suit, unless it has been made liable to be sued for negligence by legislative enactment.” That case further supports the conclusion that it cannot be successfully contended that the State Roads Commission can rightfully apply any of the funds in its hands to the payment of damages for personal injuries, and that it is not vested with any authority to raise money for that purpose. The powers of the commission were definitely prescribed and the application of funds was specifically provided, and these provisions effectually prevent its funds being diverted to purposes other than those specifically named.

These conclusions are supported in the case of Weddle v. School Commissioners, 94 Md. 334 , 51 A. 289 . In the case of Williams v. Fitzhugh, 147 Md. 384 , 128 A. 137 , suit was brought against the Board of Trustees of the State Normal School by one of the teachers for damages for an alleged breach of contract of employment. The right to maintain this suit was denied on the ground that the Board of Trustees had no means of “procuring funds beyond the amount it receives from the state treasury under budget appropriations by the General Assembly for specific uses.” To the same effect is the case of Fisher & Carrozza Bros. Co. v. Mackall, 138 Md. 586 , 114 A. 580 , and Stanley v. Mellor, 168 Md. 465 , 178 A. 106 .

The decisions in this state go further than holding that without legislative sanction an arm of the state government, such as the University of Maryland, may not be sued, and are to the effect that, even though there is a legislative authorization to sue, such

This is a preview of University of Maryland v. Maas. About 50% of the opinion remains. Read the complete opinion in RecordCite.